Buying an injection mould from China: ownership, steel, trials and transfer

Last updated

Sinospect reviews tooling and production requirements before the order and coordinates the agreed factory work in China. Send your part drawings →

This guide covers plastic injection moulds (molds, in US spelling) commissioned from a mould maker in China, whether the parts are moulded there or the mould travels to another moulder. Sinospect checked the standards, the law and the figures below at their sources on 26 and 27 September 2026.

What the buyer owns: the mould, the files and the design

A mould order buys three things that can be separated: the steel mould, the design files behind it, and the rights in the part design. A factory can hand over the mould and keep the files. Harris Sliwoski, a law firm that works on manufacturing contracts in China, advises covering each one in the agreement and settling ownership before the steel is cut.

What Chinese law says about a mould

A mould made to order falls under the contract for work (承揽合同) in the Chinese Civil Code. These articles decide who holds it and on what terms:

Civil Code articles on contracts for work and liens, translated by Sinospect from the Chinese text
ArticleWhat it says
770A contract for work covers processing and custom-made work: the contractor completes the work to the ordering party’s requirements and delivers the result.
772The contractor does the main work with its own equipment, technology and labour unless agreed otherwise. If it hands the main work to a third party, it answers for that work, and unless the ordering party consented, the ordering party may terminate.
774A contractor that supplies the materials uses the materials agreed and accepts the ordering party’s inspection of them.
783If the ordering party owes the price or the material costs, the contractor may keep the finished work or refuse delivery, unless the parties agreed otherwise.
785The contractor keeps the ordering party’s information confidential and keeps copies or technical materials only with permission.
448 and 449Between companies, the property held can answer for a debt from another transaction. Property that the contract excludes from retention stays free of it.
453Unless a period was agreed, the holder gives at least 60 days to pay before selling the property.

For a buyer, two consequences follow. A mould maker that lawfully holds the mould and is owed a debt that has fallen due can keep it, and between companies that debt can come from another order (Articles 447 and 448). The contract can take that right away, since Articles 449 and 783 give effect to what the parties agreed. The translations are Sinospect’s, from the Chinese text of the Civil Code, which prevails; a lawyer qualified in China should review the agreement itself.

The tooling agreement

The company that physically holds the mould signs the agreement, before any tooling payment. Drawing on the Civil Code and on published practitioner guidance, the agreement states:

  • the buyer’s ownership of the mould, the design files and the part design once the tooling price is paid;
  • that the mould stays free of any lien or retention, whatever the debt (Articles 449 and 783);
  • written consent before any mould shop takes on the main work, and the name of that shop (Article 772);
  • confidentiality, with copies of the mould and its files only by permission (Article 785);
  • a nameplate with the buyer’s name and an asset number, and a register with photographs;
  • use of the mould for the buyer’s parts only;
  • storage, maintenance and insurance, and how long an idle mould is kept;
  • release within a set number of days, with the handover pack;
  • damages for late release or unauthorised use, and a dispute route that works against the Chinese company.

Practitioners report what skipping it costs. Harris Sliwoski cites a buyer who paid $200,000 to recover moulds bought for $80,000 eight months earlier. QualityInspection.org reports suppliers asking 15 to 30% on top of the tooling price before releasing a mould, and recommends a Chinese-language agreement drafted by a China lawyer. FBM Sourcing reports that factories typically store a buyer’s tooling for one to two years after the last run unless a longer period is agreed, and that some scrap moulds after a storage period unknown to the buyer.

Specifying the mould: class, steel, tolerances and finish

Class. The SPI classes (SPI is now the Plastics Industry Association) grade a mould by expected life:

SPI mould classes, as published by US moulders
ClassExpected lifeTypical construction
1011,000,000 cycles and moreHardened steel, high-quality components
102Up to 1,000,000 cyclesMould base at 280 BHN minimum; cavities and cores hardened to at least 48 HRC
103Up to 500,000 cyclesPre-hardened steel
104Up to 100,000 cyclesAluminium or low-grade steel
105Prototype, about 500 cyclesCast metal, soft aluminium or epoxy

Naming the class in the order gives the steel, the components and the cycle count something to be checked against.

Steel. Quotations name steel by grade or trade name: P20 (1.2311), 718 (1.2738, a pre-hardened P20 type), stainless 420-type steels (1.2083) sold as S136 or Stavax ESR, H13 (1.2344), or NAK80. The trade names come from the steelmakers. Uddeholm’s Impax Supreme is a 1.2738 steel supplied at 290–330 HB, sold in East and South-East Asia as AS 718 Supreme. Its Stavax ESR is a stainless AISI 420 modified steel hardened to 45–52 HRC for injection moulds. Daido’s NAK80 is supplied pre-hardened to 40 HRC for mirror finishes. The name in a quotation is where the check starts; the evidence is the mill certificate traced to the blocks used, the steelmaker named on it, and a hardness reading taken on the finished mould. Article 774 gives the buyer the right to inspect the materials the mould maker supplies.

Tolerances. Both tolerance standards for moulded plastic parts changed in 2026. ISO published ISO 20457:2026 in August and withdrew the 2018 edition. In China, GB/T 47067-2026, a modified adoption of ISO 20457:2018, has applied since 1 August 2026, and GB/T 14486-2008 is withdrawn. The drawing names the standard and its edition; a quotation citing GB/T 14486 cites a withdrawn standard. ISO’s abstract of the 2018 edition places surface imperfections such as sink marks, flow structures, roughness and joint lines outside its scope, so cosmetic criteria are written separately.

Finish. The SPI finish grades run from A-1 to D-3: A grades are diamond-buffed high gloss, B grades are sanded with 600, 400 or 320 grit paper, C grades are stoned matte, and D grades are dry-blasted textures. Spark-eroded textures are specified on the VDI 3400 scale, from the German engineers’ association guideline of June 1975. The drawing gives one grade per surface.

From design review to approved sample: the gates

Each gate produces a record, and each payment follows a record.

  1. 01 Tooling agreement

    Deposit

    Signed by the company that holds the mould

  2. 02 Design review (DFM)

    DFM report, with a filling simulation if one is run

  3. 03 Mould design

    2D and 3D design approved by the buyer

  4. 04 Steel

    Mill certificate for the blocks ordered

  5. 05 T1 trial

    T1 payment

    First parts and their dimensional report

  6. 06 Corrections

    T2, T3 samples until one is approved

  7. 07 Approved sample

    Signed sample and dimensional report

  8. 08 Release inspection

    Hardness reading, cooling test, spare parts, signed acceptance report

  9. 09 Handover

    Last payment

    Design files, spare parts and process settings

Payment splits vary. Tie each payment to a record, and the last one to the signed acceptance report and the handover.
  • Design review (DFM). Wall thickness, draft angles, gate position, undercuts, parting line and shrinkage, often with a filling simulation (Autodesk Moldflow or Moldex3D) that predicts sink marks, weld lines and air traps. Approved before the steel is cut.
  • T1 and corrections. The first parts from the finished mould come with a dimensional report, and small defects are normal at this stage. The mould is corrected and sampled again (T2, T3) until a sample is approved; the signed sample and its dimensional report become the reference for production.
  • Release inspection. Steel and hardness records, cooling circuits numbered and tested, spare parts against their list, water lines drained or preserved, the data pack complete and the acceptance report signed.

Payment splits vary, for example 40% with the order, 30% at T1 samples and 30% at approval, or half with the order and half after sample approval. Whatever the split, tie the last payment to the signed acceptance report and the handover of the files.

Where moulds are made

Huangyan, in Taizhou (Zhejiang), is known as China’s home of moulds (中国模具之乡). Zhejiang Daily reported in May 2025 an annual mould output close to CNY 30 billion, 132 mould companies above the statistical size threshold, and national market shares of 80% for extrusion moulds, 75% for blow moulds and 30% for injection moulds. An MM Metalworking overview built on 2007–2008 figures describes Ningbo’s specialisms (large plastic moulds in Ninghai, precision plastic moulds in Yuyao, die-casting moulds in Beilun, household-appliance moulds in Cixi) and puts plastic and metal-stamping moulds at over 70% of Guangdong’s mould output. Sinospect’s Ningbo office is within reach of both Zhejiang clusters.

Moving a mould out of China

A mould that travels is declared under HS subheading 8480.71, moulds for rubber or plastics of the injection or compression type. Solid-wood crates follow ISPM 15, the international standard for treated and marked wood packaging; plywood and other processed-wood crates are exempt. The handover pack travels with the mould: 2D and 3D design files, steel certificates and hardness records, hot-runner documentation, the cooling layout, spare parts and their list, the final dimensional report, approved samples and the process settings from the final trial. At the new moulder, the mould runs its own first trial, measured against the drawing and the approved samples. The release deadline in the tooling agreement sets the timing.

Moulds for medical parts

For medical parts, the moulder’s quality system and cleanroom count as much as the mould. ISO 13485:2016 remains the quality management standard for medical devices (confirmed in 2025), and ISO 14644-1:2015 classifies cleanroom air cleanliness. The guides to sterile medical disposables from China and to verifying a Chinese medical device manufacturer cover the product side.

Buyer checklist

Before the first tooling payment

  • A tooling agreement signed by the company that holds the mould: ownership, files, retention excluded, subcontracting only with consent, copies only by permission, storage period, release deadline, enforcement in China.
  • The mould maker’s business licence, and the company that will hold the mould identified.
  • The class, cavity count, target cycle time and expected life in the order.

Before the steel is cut

  • The DFM report and any filling simulation approved.
  • Steel grade and steelmaker named, with a mill certificate for the blocks.
  • The tolerance standard and edition on the drawing (ISO 20457:2026 or GB/T 47067-2026), written cosmetic criteria, and one finish grade per surface.

Before release and the last payment

  • T1 report, corrections closed, approved sample signed.
  • Release inspection: hardness reading, cooling test, spare parts, data pack, signed acceptance report.
  • Nameplate and asset number fitted; register updated with photographs.
  • For a mould that travels: HS 8480.71, ISPM 15 treatment for any solid-wood crate, rust protection and the handover pack.

Frequently asked questions

Who owns an injection mould made in China?

The buyer, when a tooling agreement signed by the company holding the mould names the buyer as owner and the tooling price is paid; a lawyer qualified in China reviews that agreement. Under Article 783 of the Chinese Civil Code, a mould maker that is owed the price of its work or materials can keep the finished mould unless the contract rules this out, so the agreement comes before the first payment.

Which tolerance standard should a mould order name?

ISO 20457:2026, published in August 2026, or in China GB/T 47067-2026, in force since 1 August 2026. GB/T 14486-2008 is withdrawn. Cosmetic criteria such as sink marks and flow structures are written separately.

What is a T1 sample?

The first parts moulded from the finished mould. Small defects are normal at T1; the mould is corrected and sampled again (T2, T3) until a sample is approved and the acceptance report is signed.

Can a mould move from a Chinese factory to another moulder?

Yes, on the release terms of the tooling agreement. For export, the mould ships under HS 8480.71, in packing that meets ISPM 15 wherever it uses solid wood, with its handover pack (design files, steel records, spare parts, process settings), and runs a first trial at the new moulder.

Working with Sinospect

Sinospect’s Ningbo office is within reach of the Ningbo and Taizhou mould clusters. Before a mould order, the mould maker can be checked like any supplier: see China supplier evaluation and supplier due diligence before payment. Inventors taking a first product to production can start with the separate page for inventors.

Commissioning a mould in China?

Send the part drawings, the material, the expected annual volume and where the parts will be moulded. Sinospect reviews them and proposes the mould specification to agree and the checks each gate needs.