Skip to content

Service · Factory execution · FAT

Partial discharge (PD) test witnessing at FAT in China

Partial-discharge measurement can reveal insulation defects that a withstand test does not expose. On a buyer-direct order, Sinospect's engineer witnesses the measurement at the Chinese factory as the buyer's independent representative: circuit calibration verified, background noise recorded, voltage sequence followed, and the measured level read against the applicable contractual limit. When Sinospect supplies the equipment, the same checks are supplier-side quality control and any required independent or accredited witness remains separate.

Measurement basis
Project-specified IEC 60270 edition; limits from the approved product standard or purchase specification
Equipment class
Transformers, MV/HV and gas-insulated switchgear, instrument transformers, HV cables
Where it runs
Manufacturers' test bays and HV laboratories across China
Engagement output
Witnessed PD record inside a signed FAT witness report, with release recommendation
High-voltage transformer during commissioning

Quick answers

What does independent PD test witnessing during a FAT in China cover?

On a buyer-direct order, the independent witness verifies measuring-circuit calibration and background noise, confirms the voltage sequence against the approved project protocol, observes the measurement, and records the PD level against the contractual limit with the tested serial numbers. On a Sinospect-supplied order, these checks form part of supplier-side quality control; any required independent witness remains separate.

What the PD witness verifies before a result counts
Verification pointWhat is checkedWhy it decides credibility
Circuit calibrationCalibration under the project-specified IEC 60270 edition, performed at the actual test setupAn uncalibrated circuit makes the picocoulomb reading meaningless
Background noiseMeasured noise level recorded before the testNoise near the limit can mask or fake a pass
Voltage sequencePre-stress and measurement voltages, durations and steps per the standard or protocolPD at the wrong voltage proves nothing about the acceptance criterion
Recorded level vs limitPD magnitude read against the limit for this equipment class and specificationPass/fail must reference the correct limit, not a generic one
Unit identitySerial numbers and nameplate tied to the measurement recordThe result must belong to the unit you are releasing

Which equipment from China calls for witnessed PD testing at FAT?

Equipment whose governing standard or purchase specification sets a PD limit: power and distribution transformers, MV and HV switchgear including gas-insulated assemblies, instrument transformers, and HV cable systems and accessories. For these classes, PD reveals the insulation voids, contamination and workmanship defects that survive a pass/fail withstand test.

Equipment classes and the role PD plays at FAT
Equipment classWhat PD reveals before dispatch
Power and distribution transformersVoids, moisture and assembly defects in the insulation system
MV/HV and gas-insulated switchgearCavities, particles and stress points in solid or gas insulation
Instrument transformersInsulation workmanship on units that guard metering and protection
HV cables and accessoriesWorkmanship in insulation and prefabricated accessories before installation

01 · Scope

When witnessed PD measurement is the right control

A withstand test answers one question — did the insulation survive this voltage for this minute. PD measurement can reveal an active insulation defect that may develop in service. Because the result is a sensitive measurement rather than a survived stress, everything depends on the conditions: calibration, noise, voltage sequence, and reading the right limit. That is why specifications make PD a witnessed hold point — and why the witness must understand the measurement, not just attend it. If your contract sets a PD limit for transformers, switchgear, GIS or cables from a Chinese manufacturer, witnessing that measurement makes the contractual limit reviewable.

It becomes useful when

  • The product standard or purchase specification sets a PD acceptance limit for the units on order.
  • Transformers, MV/HV switchgear, GIS, instrument transformers or HV cable systems are bought for a project where insulation failure is intolerable.
  • A previous unit, supplier or factory has a history of marginal PD results or kindly-reported certificates.
  • The acceptance limit, test voltage or measurement practice differs between the supplier's routine and your specification.
  • A lender, insurer, EPC or end client requires independent evidence behind the PD line on the test certificate.
  • Your own HV engineers can cover the first unit at most, and the order has many.

02 · Controls and evidence

What the witness controls at the PD hold point

  • Control point

    Test basis and limit agreement

    The applicable PD limit, test-voltage sequence and measurement conditions confirmed in writing before the visit — from the product standard, the purchase specification or the agreed FAT protocol, whichever governs.

  • Control point

    Measuring-circuit calibration

    Calibration under the project-specified IEC 60270 edition witnessed at the actual test setup, with the calibration record and injected charge noted before any measurement counts.

  • Control point

    Background noise verification

    The background noise level measured and recorded before energization — and challenged when it sits close enough to the limit to mask a real result.

  • Control point

    Voltage sequence and measurement

    Pre-stress and measurement voltage steps, durations and the recorded PD magnitudes witnessed against the agreed sequence; unstable or marginal readings recorded as observed.

  • Control point

    Result, identity and disposition

    The measured level read against the correct limit, tied to the serial numbers under test; exceedances logged as non-conformities with the supplier's response and the witnessed retest tracked to closure.

Evidence reviewed

Evidence captured during witnessed PD measurement

Measurement basis record
  • Applicable standard clauses, specification limits, test-voltage sequence and measurement conditions agreed and documented before the test.
  • Test-bay setup, measuring instrument references and laboratory calibration certificates noted.
  • Witness scope recording the units, measurements and results established at FAT.
Witnessed measurement record
  • Circuit calibration and background noise recorded at the setup, before energization.
  • Voltage steps, durations and PD magnitudes recorded as observed, with the unit serial numbers photographed on the bay.
  • Anomalies — unstable readings, noise excursions, repeated runs — captured as they happen.
Disposition and release record
  • Exceedances logged with measured level, limit, voltage step and supplier response.
  • Witnessed retests after drying, reprocessing or repair recorded against the same criteria.
  • Release, hold or retest recommendation recorded as input to the contract-defined decision, inside the signed FAT witness record.

03 · Deliverables

Deliverables issued

  • Deliverable

    For · Engineering and procurement

    PD witness plan

    The agreed limit, voltage sequence, measurement conditions and witness scope before the visit.

  • Deliverable

    For · HV engineering and external reviewers

    Witnessed PD measurement record

    Calibration, background noise, voltage steps and recorded PD levels tied to unit serials — the evidence behind the certificate line.

  • Deliverable

    For · Engineering

    Photo and setup evidence

    The test setup, instruments and unit identity documented on the bay.

  • Deliverable

    For · Procurement and the supplier

    Non-conformity and retest log

    Exceedances and marginal results tracked through supplier response, correction and witnessed retest.

  • Deliverable

    For · Procurement and finance

    Release recommendation

    Release, hold or retest — the PD hold point resolved into a written recommendation for the contract-defined dispatch and payment decision.

04 · Risks controlled

Risks controlled

  • Risk

    The certificate shows a passing picocoulomb figure measured on an uncalibrated or unverified circuit.

    Control response

    The witness verifies and records calibration at the actual setup under the project-specified IEC 60270 edition before measurement.

  • Risk

    Background noise close to the limit hides real discharge activity.

    Control response

    Noise is measured and recorded first; a noise floor that compromises the limit is challenged before the test proceeds.

  • Risk

    PD is measured at a kinder voltage or a shortened sequence than the standard requires.

    Control response

    The voltage steps and durations are witnessed against the agreed sequence, and deviations are recorded as non-conformities.

  • Risk

    A marginal or unstable reading becomes a clean number by the time it reaches the certificate.

    Control response

    Readings are recorded as observed during the test, including instability and repeated runs — the record is written on the bay.

  • Risk

    The passing result belongs to a different unit, or to a type-test reference, while the units shipping stay untested.

    Control response

    Serial numbers are photographed and tied to each measurement; every unit with a specified PD hold point gets its own recorded result.

  • Risk

    Elevated PD is waved through as "within normal variation" and becomes an in-service insulation failure.

    Control response

    Exceedances are logged with the limit and the supplier's response, and carry a hold recommendation until a witnessed retest passes.

06 · Questions

Frequently asked questions

When does PD measurement belong in a FAT for equipment from China?

When the product standard or your purchase specification calls for it — typically for power transformers, MV/HV switchgear, gas-insulated equipment and HV cable systems, where insulation workmanship decides service life. If PD is specified, it should be a witnessed hold point in the FAT with the limit, test voltage and measurement conditions agreed in writing beforehand.

What makes a PD result credible rather than just a number on a certificate?

Four things the witness verifies on the bay: the measuring circuit is calibrated under the project-specified IEC 60270 edition with the record made at the actual setup; the background noise is measured; the voltage sequence follows the approved protocol; and the PD level is read against the contractual limit for that equipment class. The report records this basis instead of treating the certificate alone as acceptance evidence.

Which instruments are used for PD testing?

PD measurements use the manufacturer’s or test laboratory’s calibrated equipment. Sinospect specifies, arranges and witnesses the agreed tests for buyer-direct assignments, and carries out supplier-side quality control on equipment it supplies. Any contractually required independent or accredited witness is appointed separately.

What happens if the PD level exceeds the limit during the witnessed test?

The exceedance is recorded with the measured level, the applicable limit, the voltage step and the background noise, and logged as a non-conformity. Typical supplier responses — locating the source, drying, reprocessing, repair and retest — are tracked, and the witnessed retest must pass the same criteria. Elevated PD normally supports a hold recommendation. On a buyer-direct order, the buyer makes the release decision under its contract. On a Sinospect-supplied order, Sinospect records a supplier-side quality-control disposition; buyer acceptance and any payment or shipment consequence follow the signed contract.

Can PD witnessing be combined with witnessing the rest of the FAT?

Yes, and that is the efficient shape. PD is one hold point inside the wider FAT scope — identity checks, routine electrical tests, function and documentation review. One witnessed visit covers the full agreed protocol; this page exists because PD is the point where independent verification of the measurement conditions matters most.

07 · Getting started

What to send — start with what you have

The purchase specification and the equipment class are enough to start; the PD limit and sequence are confirmed from the governing standard where your documents do not state them.

  1. Purchase specification or datasheet

    The equipment class, ratings and the standards the units were bought against.

  2. PD requirement, if stated

    The limit, test voltage and any measurement conditions your contract sets — or the standard it defers to.

  3. FAT protocol or test plan, if one exists

    Where PD sits in the wider test sequence, so one visit witnesses the whole hold-point scope.

  4. Purchase order and manufacturer details

    Units, serial quantities and the test-bay location, so the visit can be arranged.

  5. Expected test-readiness window

    When the manufacturer expects the units on the bay, so witnessing is booked before dispatch pressure builds.

Send the documents available. Sinospect confirms the governing limit and sequence, and what is missing.

Arrange witnessing for your PD hold point

Send the specification, equipment class and expected test window. On a buyer-direct order, Sinospect can propose an independent China-side witness; on a Sinospect-supplied order, the work is supplier-side quality control. Sinospect acknowledges the request within one business day. When the file is sufficient, the initial written assessment follows within two business days with the proposed scope, a quotation and the earliest feasible attendance. The measurement runs on the laboratory's calibrated instruments, verified on the bay.