Skip to content

Checklist · Factory execution

Factory acceptance test checklist for industrial equipment in China

A factory acceptance test, or FAT, is one of the last practical opportunities to confirm that industrial equipment meets the purchase specification before it leaves the supplier’s factory. For China-sourced equipment, the FAT should not be treated as a supplier presentation or a simple “machine running” demonstration — it should be a controlled procurement hold point with defined acceptance criteria, equipment identification checks, witnessed tests, documented results, non-conformity follow-up and a clear release or hold decision.

For broader background, see Sinospect’s guide to factory acceptance testing and the explainer what is a factory acceptance test?

When to use this FAT checklist

Use this checklist when buying custom, semi-custom, engineered or project-specific industrial equipment from a Chinese supplier. It is especially useful when:

  • The equipment has custom specifications, drawings, performance requirements or configuration options.
  • The buyer cannot send their own team to the factory.
  • The equipment is expensive, bulky, difficult to return or costly to rework after arrival.
  • The supplier must complete corrective actions before packing or shipment.
  • The FAT result will decide whether the order is released, held or partially accepted.
  • A later pre-shipment inspection checklist will be used to confirm final packing, marking, quantity and shipment readiness.

A FAT checklist should be agreed before the FAT date. It should not be written only after the inspector arrives at the factory.

Printable factory acceptance test checklist

The twelve sections below can be copied into a project file, inspection request, supplier communication or FAT report template. Each section closes with a procurement-control point — the principle a buyer should not let the supplier compromise.

01

Before FAT is scheduled

Confirm that the supplier is actually ready for FAT before sending an inspector, buyer representative or third-party witness to the factory.

  • Supplier confirms equipment assembly is complete.
  • Supplier confirms FAT can be performed on the exact equipment ordered.
  • Equipment is available at the factory and not already packed.
  • Utilities, test media, fixtures, loads or simulation setup are available as agreed.
  • Required measuring instruments and test equipment are available.
  • Supplier confirms test personnel will be present.
  • Buyer-approved drawings and specifications are available at the factory.
  • FAT procedure and acceptance criteria are agreed before the test date.
  • Inspection access, photo permission and document access are confirmed.
  • Supplier agrees that open critical or major non-conformities may block release.
  • FAT date is scheduled before final packing, shipment booking or balance payment.
02

Documents to request before FAT

Request the FAT document set before the test. Missing documents often cause weak FAT execution because the inspector has nothing objective to verify against.

  • Purchase order and technical specification.
  • Approved general arrangement drawings.
  • Approved electrical, hydraulic, pneumatic or control drawings, if applicable.
  • Bill of materials or key component list.
  • Inspection and test plan, if used.
  • FAT procedure or test protocol.
  • FAT acceptance criteria.
  • Nameplate data or nameplate artwork.
  • Calibration certificates for measuring instruments used during FAT.
  • Material certificates, welding records, NDT records or pressure-test records, if contractually required.
  • Key bought-out component certificates or datasheets.
  • Software, PLC, HMI, firmware or configuration version information, if applicable.
  • Packing list draft.
  • Spare-parts list.
  • Operation and maintenance manual draft, where required by the purchase order.
  • Previous non-conformity reports or corrective-action records related to the equipment.
03

Test plan and acceptance criteria

A FAT without acceptance criteria is only a demonstration. Before FAT, the buyer and supplier should define what will be checked, how it will be checked, and what result is acceptable.

  • FAT scope is defined.
  • Each test has a measurable acceptance criterion.
  • Critical performance parameters are included.
  • Required test duration is defined.
  • Test conditions are defined.
  • Load, no-load, simulation or utility conditions are specified where relevant.
  • Instruments used for measurements are identified.
  • Sampling method is defined for multiple units.
  • Retest rules are defined for failed items.
  • Criteria for release, conditional release and hold are agreed.
04

Equipment identification and serial numbers

Before witnessing any test, confirm that the equipment being tested is the equipment ordered.

  • Manufacturer name matches purchase records.
  • Buyer name, project number or order reference is confirmed, if applicable.
  • Equipment model matches the purchase order.
  • Serial number is present and recorded.
  • Nameplate data matches the agreed specification.
  • Tag numbers match drawings or project list.
  • Quantity of units matches order or FAT scope.
  • Key component serial numbers are recorded where required.
  • Motors, pumps, sensors, PLCs, drives, instruments or other key components match the approved list.
  • Drawing revision used during FAT is recorded.
  • Equipment configuration matches the approved option list.
05

Visual and dimensional checks

Visual and dimensional checks confirm that the equipment is complete, correctly built and consistent with the approved design before functional testing.

  • Overall equipment layout matches the approved drawing.
  • Main dimensions match the approved drawing or tolerance table.
  • Mounting points, anchor holes, flanges, interfaces or connection points are checked.
  • Material, finish and surface treatment match the specification.
  • Weld appearance is checked where applicable.
  • Paint or coating condition is checked for visible defects.
  • Fasteners, guards, covers, doors and panels are present.
  • Cable, hose and pipe routing is visually checked.
  • Labels, warning plates, flow-direction marks or terminal marks are present where specified.
  • Accessibility for maintenance points is checked against specification, where applicable.
  • No visible damage, deformation, corrosion, missing parts or poor workmanship is observed.
  • Any cosmetic or workmanship defects are photographed and recorded.
06

Functional test witnessing

Functional test witnessing is the core of FAT. The purpose is not just to see the machine run — it is to verify agreed functions and performance against the FAT procedure.

  • FAT starts with confirmed equipment identification.
  • Test setup is recorded.
  • Test conditions match the agreed FAT procedure.
  • Supplier performs each test in the agreed sequence, where required.
  • Inspector witnesses the test directly.
  • Actual measured values are recorded, not only pass / fail results.
  • Key functions are demonstrated.
  • Control panel, HMI, indicators and alarms are checked where applicable.
  • Start, stop, reset, changeover and operating modes are checked where applicable.
  • Interlocks or protection functions are checked where specified.
  • Leakage, pressure, speed, temperature, vibration, noise or output values are checked where specified.
  • Test duration meets the agreed procedure.
  • Abnormal interruptions, resets, alarms or supplier adjustments are recorded.
  • Deviations from the FAT procedure are documented.
  • Failed test items are retested only after corrective action is completed.
07

Safety, accessories and spare-parts checks

This section is a procurement checklist for confirming that specified safety-related features, accessories and spare parts are present before release — it is not a safety manual.

  • Specified guards, covers, barriers or protective devices are installed.
  • Emergency-stop devices are present where specified.
  • Safety labels or warning plates are present where specified.
  • Electrical cabinet layout and labelling are checked against drawings, where applicable.
  • Grounding, cable marking or terminal marking is checked where specified.
  • Accessories listed in the purchase order are present.
  • Tooling, fixtures, change parts, connectors or adapters are present where ordered.
  • Spare-parts list matches the purchase order or contract.
  • Spare parts are physically checked, counted and photographed where possible.
  • Consumables or wear parts included in the order are identified.
  • Certificates or declarations required by the buyer are available.
08

Documentation and test-record review

The FAT report should contain objective records the buyer can use for release control and future reference, not just a supplier statement that the equipment passed.

  • FAT report includes equipment model and serial number.
  • FAT report includes purchase order or project reference.
  • Test date, location and attendees are recorded.
  • Test procedure revision is recorded.
  • Drawing revision is recorded.
  • Actual measured values are included.
  • Instrument details or calibration references are included where relevant.
  • Photos show nameplates, full equipment view, key components and test setup.
  • Videos are labelled or organised by test item where useful.
  • Non-conformities are listed with status.
  • Open items are clearly identified.
  • Supplier comments are separated from inspector findings.
  • Buyer decision is recorded as release, conditional release or hold.
09

Non-conformity handling

FAT non-conformities should be handled formally. The supplier may suggest fixing issues later, but the buyer needs clear records and objective closure evidence.

  • Each non-conformity is described clearly.
  • Each non-conformity is linked to a specification, drawing, order requirement or FAT criterion.
  • Each issue is classified by severity: critical, major or minor.
  • Photos, videos or test records support the finding.
  • Supplier response is recorded.
  • Corrective-action owner is identified.
  • Target completion date is agreed.
  • Retest requirement is defined.
  • Open non-conformities are included in the release / hold decision.
  • Buyer approval is required before closing major or critical items.
10

Corrective-action evidence

Corrective action is only useful when the buyer can verify it. Evidence should show that the specific issue was corrected on the specific equipment being purchased.

  • Corrective action is linked to the original non-conformity.
  • Supplier explains the correction made.
  • Before-and-after evidence is provided where applicable.
  • Corrected area is photographed with equipment ID or context.
  • Failed functional test is repeated after correction.
  • Retest results are recorded with actual measured values.
  • Updated drawings, documents or records are provided if changes were made.
  • Corrective action is verified by buyer, inspector or authorised representative.
  • Non-conformity status is updated to open, closed or conditionally accepted.
  • Remaining open items are listed before release decision.
11

Release or hold decision

The FAT should end with a clear procurement decision based on evidence, not on supplier pressure, shipment urgency or balance-payment timing.

  • All critical FAT items passed.
  • All major non-conformities are closed or formally accepted by buyer.
  • Minor open items are listed and accepted by buyer, if any.
  • Required documents are complete or open items are listed.
  • Accessories and spare parts are verified or exceptions are listed.
  • Corrective-action evidence has been reviewed.
  • Buyer release condition is documented.
  • Supplier is instructed whether to pack, hold, rework or retest.
12

Post-FAT document pack

After FAT, the buyer should receive a complete document pack before authorising final packing, shipment or balance payment.

  • FAT report.
  • Signed or acknowledged test record.
  • Equipment identification record.
  • Nameplate photos.
  • General equipment photos.
  • Key component photos.
  • Functional test photos or videos.
  • Measurement records.
  • Calibration certificates for test instruments, where relevant.
  • Non-conformity list.
  • Corrective-action evidence.
  • Retest evidence, if applicable.
  • Updated drawings or as-built documents, if applicable.
  • Packing list draft.
  • Spare-parts verification record.
  • Open-item list, if any.
  • Final release / hold recommendation.

Severity classification — non-conformities

  • Critical

    Equipment cannot meet essential specification, safe handling requirement or agreed core function.

    Hold release.

  • Major

    Equipment may function, but a required specification, test result, component or document is missing or failed.

    Usually hold until corrected and verified.

  • Minor

    Issue does not affect agreed core function or shipment risk, but should be corrected or documented.

    May allow conditional release if buyer accepts.

What buyers should not accept as sufficient FAT evidence

The following evidence may be useful as supporting material, but it should not be accepted as sufficient proof of FAT completion on its own.

  • Short video of equipment running.

    Why it is not sufficient · Does not prove the exact unit, test conditions, duration or acceptance result.

  • Supplier statement saying “FAT passed”.

    Why it is not sufficient · No independent evidence, measurements or traceability.

  • Photos without nameplate or serial number.

    Why it is not sufficient · Cannot confirm the photographed unit is the ordered equipment.

  • Internal QC checklist with only pass / fail marks.

    Why it is not sufficient · May not show actual values, test conditions or buyer criteria.

  • Test records without instrument details.

    Why it is not sufficient · Measurements may not be reliable or repeatable.

  • Certificates for a different model or batch.

    Why it is not sufficient · Not traceable to the equipment being purchased.

  • “We will fix before shipment” message.

    Why it is not sufficient · No closure evidence or retest proof.

  • Packed equipment photos after FAT issues.

    Why it is not sufficient · Packing does not prove non-conformities were closed.

  • Old drawings or outdated specifications.

    Why it is not sufficient · FAT may be performed against the wrong revision.

  • Verbal explanation from supplier staff.

    Why it is not sufficient · Not usable as release evidence or later claim support.

The buyer should require traceable, dated, equipment-specific evidence. For important orders, a third-party FAT witness can reduce the risk of accepting incomplete or misleading supplier evidence.

Common FAT red flags in China-sourced equipment

These red flags do not always mean the equipment is unacceptable, but they should trigger closer control before release.

  • Supplier wants to schedule FAT before the test plan is agreed.

    Why it matters · The FAT may become a demonstration instead of an acceptance test.

  • Supplier refuses to share drawings, test records or calibration documents.

    Why it matters · The inspector may not be able to verify objective requirements.

  • Equipment has no serial number or unclear identification.

    Why it matters · FAT evidence may not be traceable to the shipped unit.

  • Supplier says some tests can only be done after shipment.

    Why it matters · Buyer may lose leverage once equipment leaves the factory.

  • Only no-load testing is offered despite performance requirements.

    Why it matters · Core functional risk may remain unverified.

  • Supplier changes components without buyer approval.

    Why it matters · Equipment may not match the agreed specification.

  • The factory performs tests before the witness arrives and only shows records.

    Why it matters · The buyer loses direct witnessing evidence.

  • Measured values are not recorded.

    Why it matters · The report cannot prove compliance against acceptance criteria.

  • Supplier asks for release with open major issues.

    Why it matters · Corrective action may be delayed until after shipment.

  • Accessories or spare parts are “not ready yet”.

    Why it matters · Installation or commissioning delays may occur after delivery.

  • Equipment is already packed before FAT.

    Why it matters · Visual, identity and functional checks may be blocked.

  • Supplier pressure is tied to vessel booking or balance-payment deadline.

    Why it matters · Commercial urgency may compromise technical release control.

A strong FAT process identifies these issues before the equipment is released. A weak FAT process often discovers them after the equipment has already shipped.

FAT and pre-shipment inspection — how they work together

A factory acceptance test and a pre-shipment inspection are related, but they are not the same. A factory acceptance test checks whether the equipment meets agreed technical, functional and documentation requirements before release; it focuses on performance, configuration, identity, test records and non-conformity closure. A pre-shipment inspection checks whether the final goods are ready to ship; it focuses on quantity, packing, marking, loading readiness, visible condition, shipment documents and final order conformity.

For industrial equipment sourced from China, the strongest control sequence is usually:

  1. Agree FAT scope and acceptance criteria.
  2. Conduct FAT before final packing.
  3. Record non-conformities and corrective actions.
  4. Verify corrective-action evidence.
  5. Issue release, conditional release, hold or retest decision.
  6. Conduct pre-shipment inspection after final packing is complete.
  7. Authorise shipment only when FAT and PSI evidence support release.

A pre-shipment inspection should not be used as a substitute for FAT when the equipment has custom performance requirements. By the time equipment is packed, some functional tests may be difficult or impossible to witness properly. For shipment-readiness planning, use Sinospect’s pre-shipment inspection checklist.

What Sinospect checks during a China FAT

Sinospect supports buyers who need independent factory-side control during FAT for China-sourced industrial equipment. During a FAT engagement, Sinospect can verify whether the supplier is ready before the visit, whether the equipment being tested matches the purchase order and approved configuration, whether the agreed FAT procedure is followed, whether functional tests are witnessed with measured values rather than vague pass / fail statements, whether visual, dimensional, accessory, spare-parts and documentation checks are completed, whether non-conformities are documented with clear evidence, whether corrective actions are verified before release, and whether the buyer should release, conditionally release, hold or require retesting.

For service details, see factory acceptance testing in China. For anonymized examples of FAT findings, escalations and dispositions on real engagements, see selected field notes.

Frequently asked questions

What is included in a factory acceptance test checklist?

A FAT checklist should include supplier readiness, document review, test plan confirmation, acceptance criteria, equipment identification, serial-number checks, visual and dimensional inspection, functional test witnessing, accessory and spare-parts checks, documentation review, non-conformity handling, corrective-action evidence, release / hold decision, and the final FAT document pack.

When should the FAT checklist be agreed with the Chinese supplier?

The FAT checklist should be agreed before the FAT date is scheduled. The buyer should confirm the FAT scope, required documents, test conditions, acceptance criteria and release rules before sending a representative or third-party inspector to the factory.

Is a supplier video enough for FAT approval?

Usually no. A supplier video may support the FAT record, but it should not replace witnessed testing, equipment identification, measured results and documented acceptance criteria. A short video often does not prove the exact unit, test setup, test duration or compliance result.

What documents should a buyer request before FAT?

The buyer should request the purchase order, technical specification, approved drawings, approved component list, FAT procedure, acceptance criteria, inspection and test plan, calibration certificates, nameplate information, spare-parts list, packing list draft, and any contractually required material, welding, NDT, pressure-test or component records.

What is the difference between FAT and pre-shipment inspection?

FAT verifies whether the equipment meets agreed technical, functional and documentation requirements before release. Pre-shipment inspection verifies final shipment readiness — quantity, packing, marking, visible condition and order conformity. For complex industrial equipment, FAT and pre-shipment inspection are complementary controls.

Can FAT be performed remotely?

Some FAT evidence can be reviewed remotely, but remote FAT has limitations. The buyer should be cautious if remote FAT relies only on supplier-controlled videos, photos or internal reports. When the equipment is high-value, custom or technically complex, on-site witnessing at the Chinese supplier’s factory gives stronger release evidence.

What should happen if the equipment fails FAT?

Failed FAT items should be recorded as non-conformities. The supplier should provide corrective action, and the buyer should require evidence of closure. For functional failures, the relevant test should usually be repeated. Major or critical issues should normally block release until corrected and verified.

Who decides whether equipment is released after FAT?

The buyer makes the commercial release decision. The supplier provides test results, and an inspection partner such as Sinospect provides independent factory-side evidence, non-conformity status and a release / hold recommendation.

Should FAT be done before or after packing?

FAT should usually be done before final packing. Once equipment is packed, important identity, visual, dimensional, accessory and functional checks may be difficult or impossible to perform properly. Pre-shipment inspection can then be performed after packing to verify shipment readiness.

How does Sinospect support FAT in China?

Sinospect supports FAT in China by checking supplier readiness, witnessing agreed tests, verifying equipment identity and serial numbers, reviewing documents and test records, reporting non-conformities, following corrective actions and helping the buyer decide whether to release, conditionally release, hold or require retesting.

Need FAT support at a Chinese supplier’s factory?

Send the equipment scope, the supplier’s inspection and test plan if it exists, and the FAT window. Sinospect responds with the witnessing approach, the document pack the buyer should expect, and the team that would attend.