FAT vs SAT: tests for equipment made in China
Last updated
Sinospect supplies the equipment from China as the principal and runs the FAT as its own release gate, or witnesses the FAT and SAT for a purchase you make direct. Send your FAT or SAT plan for review →
Acceptance chain
FAT is one controlled handoff in a five-step chain
Each step answers a different question. Skipping the written release or the factory-to-site record leaves the SAT team without a reliable baseline.
- 01
FAT
Witness the contract tests at the manufacturer’s works.
- 02
Release
Close blocking findings and record the authorised release decision.
- 03
Ship
Verify preservation, packing and what actually leaves.
- 04
Install
Connect utilities, interfaces and commission at site.
- 05
SAT
Test integrated performance under real site conditions.
If you have just been handed a purchase order and asked to “arrange the FAT and the SAT”, and neither term means anything yet: they are two inspections of the same equipment at two different moments. The FAT happens at the factory that built it, before it ships; the contract may tie a payment milestone to it. A factory witness test may be the same visit only when the protocol, acceptance criteria, witness role and authority define it as the FAT; source inspection and vendor surveillance are broader programmes that may include the FAT as one witness point. The SAT happens at your own site, after the equipment is installed and running. Everything below is the detail of who does what at each, and what each signature costs you if it is given too early.
The two tests sit at opposite ends of the delivery chain and commit the buyer to different things when signed. International practice treats them as distinct, defined acceptance events, and IEC/ISA 62381 covers both. Yet purchase contracts routinely collapse them into a single vague “acceptance test”, and that is where disputes start. This guide covers what each test verifies, what each signature triggers, and why the gap between them is where acceptance problems live. For the factory test itself in depth, see the companion guide What is a factory acceptance test for industrial equipment?
For the defect and hold categories that need coverage across the factory stage, see Sinospect’s qualitative China FAT and PSI defect-pattern control guide.
What a FAT covers, and where it happens
The FAT takes place on the supplier’s factory floor, once manufacturing and internal QC are complete and before anything is packed for transport. It runs against an approved FAT procedure with defined test steps, acceptance criteria and sign-off rules, agreed before the test date. The factory’s own test runs before the visit are normal preparation, but a test the plan requires to be witnessed has to be run again in front of the witness; if the unit is already packed, some checks are blocked entirely. Sinospect’s factory acceptance test checklist sets out those steps: readiness, identity, functional witnessing, non-conformities and the release decision, section by section.
A properly scoped FAT verifies three layers:
Build. Dimensional checks against approved drawings, including interface points: flange ratings, facings and drilling patterns checked against the approved interface drawings, not against whichever revision the workshop happened to build from. Materials verified against certificates, nameplates, tag numbers, completeness against the bill of materials, surface treatment and preservation readiness.
Function. Dry runs and, where practical, load runs; control sequences, cycle times, alarms, emergency stops and safety interlocks checked against the project control philosophy, not just the supplier’s standard demonstration; electrical panel inspection against schematics, including control voltages. For high-voltage equipment such as transformers and switchgear, type-specific checks like partial discharge testing during FAT sit in this layer, with their own limits and witnessing rules. On one packaged skid, the main motor data can match the purchase order while an auxiliary control panel has been built for the wrong site control voltage, invisible during the factory run because the supplier tested through a temporary transformer. At site it stops energisation, forces panel rework and delays commissioning even though the equipment appeared to run in the factory.
Documentation. Manuals, calibration certificates, material certificates, as-built wiring drawings, lifting instructions and spare parts lists reviewed against the contractual documentation list. An equipment package can be technically present and still not be ready for site: missing as-built drawings or calibration records do not stop a factory demonstration, but they stop installation, energisation or handover.
A FAT is also the moment to confirm something no factory run answers: whether the package can be installed, operated and maintained in the position shown on the project layout. A filter housing or junction box that will face a wall or an adjacent package at site is a real finding, caught by checking the general arrangement drawing, and it becomes very expensive to discover after the equipment is grouted in.
Conditions at FAT are the factory’s: stable utilities, substitute media, simulated signals, often partial load. That is the FAT’s limitation, and also its value: findings can be addressed by the people who built the machine while it remains on their premises. Where the contract links corrective work, shipment and payment to the agreed FAT outcome, this is an important pre-shipment leverage point. Whether open findings justify a hold or release is decided by the party the contract assigns, and a deviation from the buyer’s specification still needs the buyer’s approval.
What a SAT covers, and where it happens
The SAT takes place at the buyer’s site, after the equipment has been delivered, installed and connected, and during or after commissioning as the contract sets. Where the FAT asked whether it was built to specification, the SAT asks whether it performs to specification here.
A serious site acceptance test checklist covers:
- Delivered condition: transport damage, serial-number match against the FAT report, preservation state on arrival.
- Installation: foundation, anchoring, levelling, alignment, reassembly of items removed for transport, guarding reinstated.
- Utilities as found: actual voltage, frequency and power quality at the terminals; compressed air, cooling water, drainage; not the datasheet values, the values available on the day.
- Function as installed: the sequences, interlocks and alarms checked at FAT, re-run with site utilities and field wiring.
- Performance: runs with the real process medium at contractual capacity, sustained over an agreed duration.
- Integration: signal exchange with upstream and downstream equipment and the plant control system, safety circuits checked across vendor boundaries.
- Handover: operator and maintenance training delivered, manuals on site, commissioning spares received.
Site conditions are not the factory’s: site power may sag, ambient heat, humidity and dust differ from the factory floor, and the product behaves differently from the test medium. That is the point: the SAT is the acceptance test intended to run under the agreed site conditions in which the equipment will operate, with the actual conditions recorded.
The effect of the SAT record depends on the contract. It may support final acceptance, payment, warranty commencement or a transfer of care, custody and control only where the agreed terms assign those consequences. The buyer, or the party the contract names for site acceptance, decides acceptance and deviations and should record how every open punch item is to be resolved before signing.
FAT vs SAT at a glance
| Factory acceptance test (FAT) | Site acceptance test (SAT) | |
|---|---|---|
| Location | Supplier’s factory | Buyer’s project site |
| Timing | After manufacture, before packing and shipment | After delivery and installation; during or after commissioning, as the contract sets |
| Conditions | Controlled: factory utilities, substitute media, simulated signals | Real: site power, real process media, live interfaces, site ambient |
| Who attends | Buyer’s engineer or appointed witness; supplier QC and project engineer | Buyer’s engineering and operations team; supplier’s commissioning engineer; other vendors where interfaces are tested |
| What is tested | Build against drawings and specification; function under factory conditions; documentation pack | Installed condition, utilities, integration and performance under site conditions; handover readiness |
| Evidence produced | Witnessed FAT report, punch list, test and calibration records | SAT report, performance run data, commissioning records, training and handover sign-offs |
| What signing commits you to | Whatever the contract assigns: often shipment release and a payment milestone; not final acceptance unless expressly stated | Only what the contract assigns: it may support final acceptance, final payment, warranty start or transfer of care, custody and control |
| Typical failure categories | Dimensional and interface errors, wrong or unverified materials, missing items, control logic faults, documentation gaps | Transport damage, installation errors, utility mismatches, integration faults, performance shortfall under real load |
| Who pays for failures found here | As allocated by the contract and verified root cause; the terms should also assign re-test and witness re-attendance costs | As allocated by the contract and verified root cause; site costs such as cranage, idle crews and delay should be addressed expressly |
Which of the two you actually need help with
This comparison is usually read while a decision is waiting. Below is where an order usually sits when someone looks the difference up, the question underneath it, and the shortest route to an answer.
| Where the order is | The question underneath it | Where to look next |
|---|---|---|
| Nothing ordered yet; the contract is still being drafted | How do I word the acceptance sequence so that FAT and SAT each mean something? | The factory acceptance testing guide: sequence, evidence, and how release is recorded |
| Order placed, FAT date approaching | Who attends, and what has to be agreed in writing before the test date? | The twelve-section FAT checklist |
| Nobody on our side can travel to China for the test | Can someone attend on our behalf, and is a delegated witness worth anything? | What delegated witnessing has to mean to be worth delegating |
| The supplier says the test passed | Is that record strong enough to release a payment milestone against? | Where the written record lives: the controlled order package |
| It is a bought-out package on an EPC project | Our procedure calls this source inspection or vendor surveillance — where does the FAT sit inside it? | Witnessing bought-out EPC procurement packages |
| Equipment has shipped; the SAT is ahead of us | The SAT is my own team’s job — what should the factory record already have given us? | The document-control method: what the factory file hands the site team |
One thing worth separating before any of those: the SAT takes place at your site and is run by the party the contract assigns, whether your own team, an integrator or the supplier’s commissioning engineer. The FAT is the one of the pair that happens in somebody else’s building, on somebody else’s schedule, in a country where you may have nobody — which is why it is the half of the sequence buyers most often need to arrange rather than simply attend.
What does a FAT date mean in a project schedule?
A FAT date is the date the supplier commits to having the equipment assembled, internally tested and ready for witnessed factory acceptance. It anchors everything downstream of it: witness travel, vessel booking, letter-of-credit milestones, site readiness. That makes FAT-date slippage a reliable signal that delivery will be late.
In procurement documents, “FAT date” normally refers to the factory acceptance test; it is unrelated to the FAT (File Allocation Table) date format used in computing. A supplier that reschedules the FAT date more than once is signalling a delivery risk, and the shipment milestone should follow the witnessed test, not the original calendar.
Why “passed FAT” does not mean “will pass SAT”
Between the factory floor and site sign-off, five things change. Each can turn a clean FAT report into a failed SAT.
Transport and handling. Weeks at sea, multiple lifts, storage at both ends, often handled by parties who were never in the factory. Vibration loosens terminals, moisture finds unsealed enclosures, a bad lift bends a frame. And a passed FAT does not protect the buyer if the equipment is not preserved for transport: open nozzles, unsealed glands and unprotected machined surfaces can turn a factory-accepted package into an arrival-damage dispute. A clean FAT report should be followed by packing checks, arrival inspection and preservation records, not treated as the final condition report.
Installation variables. At FAT the machine stood on the supplier’s prepared floor, assembled by the people who built it. At site, foundations, grouting, levelling and reassembly are executed by a local contractor working from drawings, and the package is connected to long pipe runs, field cables and adjacent equipment the factory never reproduced. Misalignment, pipe stress and vibration often appear only after installation.
Utilities. The FAT ran on stable factory power, dry instrument air and clean water. The site may offer generator power with voltage dips, a different supply standard, humid air and hard water. FAT documents performance under recorded factory conditions; SAT checks whether the same package works with the real utilities available at site, which is why the FAT procedure should record exactly what temporary utilities were used.
Integration. At FAT, external signals are simulated with jumpers, switches or test software. A package may pass a local start-stop demonstration while still missing a permissive, alarm or trip required by the project control philosophy, an issue that belongs in the FAT punch list, not in the site commissioning room. At SAT the simulations disappear: the package must exchange live handshakes with other vendors’ equipment and the plant control system. Multi-vendor lines fail at the seams, not inside the machines. The closer the FAT simulation is to the real site interface, the fewer surprises the commissioning team faces at SAT.
Ambient. Temperature, humidity, dust and altitude, none of them present in the factory test. For equipment shipping to high-ambient or high-humidity sites, performance can deviate measurably from the bench result.
What bridges the gap is unglamorous and contractual: a marine packing specification verified at pre-shipment inspection; a utilities and interface schedule frozen at design review and signed by both sides, so “site conditions” cannot later serve as a defence; a controlled technical review whenever the project design changes after FAT documents are frozen; supplier commissioning attendance with rates agreed in advance; and commissioning spares shipped with the unit, not ordered after the first failure. With those measures in place, the SAT confirms what the factory record already showed rather than surfacing problems for the first time at site, where they are most expensive to fix.
FAT, SAT and commissioning: what the factory record has to hand over
Buyers rarely think about the two acceptance tests on their own. They think about a sequence of factory acceptance test, site acceptance test and commissioning, and the contract decides the order of the site steps and who runs each one. The FAT happens at the manufacturer’s works. The SAT and the commissioning happen at your site, run by whoever carries that scope — your project team, your integrator, or the supplier who sold you the equipment.
What travels between the two halves is a record. So the useful question is not who does what — it is what the factory test has to capture so that the people commissioning the plant are not rediscovering it on site, where correction costs the most and the supplier is no longer in the room.
| What the FAT records | What it lets the site team do | What happens when it is missing |
|---|---|---|
| As-tested configuration | Serial numbers, software and firmware revisions, and the parameter set actually loaded on the day — so the site team commissions the machine that was tested. | Unexplained behaviour at site with no baseline to show whether something changed after the test. |
| Utilities and simulation | Temporary utilities used, signals forced or shunted, load actually applied — written into the report rather than left to the memory of whoever attended. | A passed FAT read as proof of performance, until the first run on real load. |
| Settings and parameters | Protection settings, control-loop tuning, timers and safety-circuit configuration as left at the end of the test. | Hours of blind re-tuning, with no supplier record to argue against. |
| Interfaces and signals | The signals actually exchanged during the test, read against the project control philosophy. The gap between the two is the integration risk list. | Defects surface at the seams during integrated testing, when the schedule has no float left. |
| Calibration | Instrument references and calibration validity for every measured value in the report. | Disputed factory readings cannot be relied on until the instrument’s calibration status is verified or the test is repeated. |
| Punch list | Every item with its category, owner and closure date — including the ones deliberately carried to site. | Open items have no agreed owner or closure date, so closing them after payment depends on the remedies left in the contract. |
| Documents and spares | The document pack as it actually stands at the factory gate: as-built and manual revisions, and the commissioning spares actually loaded into the container. | A gap discovered when the crates are opened, with the commissioning team already on site. |
Three things a factory test can never prove, however carefully it is run: performance under the utilities actually available at site, live integration with other vendors’ equipment, and behaviour in the real ambient. Those belong to the SAT and to commissioning. What the FAT can do is name them explicitly, so they reach the commissioning schedule as tasks rather than as surprises.
Sinospect works on the factory side of that sequence: it witnesses the test in China and assembles the record. Where Sinospect supplies the equipment itself, that responsibility does not stop at the factory gate — seeing the machine through to service on site, within the delivery and support scope agreed in the supply contract, is part of the supply, not a separate engagement. Standalone site commissioning belongs to an integrator or a commissioning contractor.
FAT and SAT on a regulated line
On a pharmaceutical or biotech line, or any line where the end user’s quality system requires qualification, neither test is qualification. Qualification — installation, operational and performance qualification, IQ, OQ and PQ — is the end user’s own regulated exercise, run against protocols owned by the end user’s quality system and defended in the end user’s audits. What the FAT and SAT do is generate evidence that qualification can lean on instead of repeating.
That changes what the factory record has to look like. A FAT report adequate for a general industrial buyer — “tests performed, results acceptable” — cannot be cited inside a qualification protocol. What can be cited is dated and signed, identifies the exact unit by serial number, names the test instrument with its calibration status, and states the acceptance criterion beside the measured value or references the approved document that defines it. The equipment’s own documentation set — material certificates, surface-finish records, drawings, software and firmware revisions — should be assembled at FAT as far as the contract requires, with anything that can only be finalised later listed with its owner and due date, because every one of those is easier to obtain while the equipment is still on the supplier’s floor than after it is installed in a controlled area.
Sinospect does not write, approve or execute qualification protocols; that stays with the end user’s quality organisation. The factory-side job is to make sure the record arriving from China is in a form qualification can consume. For cleanroom and controlled-environment packages, where part of the acceptance is only provable once the system is installed, the boundary between what is verifiable at the works and what is genuinely site-only is set out under cleanroom systems FAT witnessing.
When the contract should require both, and how to word the acceptance sequence
Both tests are justified whenever equipment is engineered to order, contains automation, depends on site conditions for its performance, or crosses an ocean. For a standard catalogue machine, a FAT combined with a pre-shipment inspection may be enough; for anything engineered, the acceptance sequence should be explicit in the purchase contract rather than assembled from assumptions after the order.
One clean sequence reads: FAT → release for packing → pre-shipment inspection → release for shipment → delivery → installation → commissioning and SAT → final acceptance certificate → warranty start. The contract may order the site steps differently or start the warranty from another named event. Each arrow should map to defined evidence and, where money moves, a payment milestone.
The classic dispute is the supplier arguing that the FAT signature meant final acceptance, usually after the package fails SAT on an interface problem. The defence is built into the contract before the order is signed:
Wording points that decide outcomes later:
- Attach the FAT and SAT protocols as contract annexes, agreed before manufacture starts. A test protocol negotiated at the factory gate is the supplier’s protocol.
- Categorise punch items before shipment release, because “minor open items” is not a definition. A workable scheme: Category A must be closed before shipment; Category B before energisation; Category C may remain open until SAT without affecting safe installation; Category D covers documentation and cosmetic items with an agreed closure date. Items affecting safety, core function, site interfaces, statutory compliance, preservation or commissioning documentation belong in Category A unless the buyer authorises another category in writing; that approval cannot waive a statutory or safety requirement.
- Name the test in every payment milestone. “Payment after acceptance test” is an invitation to dispute: a payment due after FAT should be linked to the signed factory acceptance and closure of shipment-blocking items; a payment due after SAT to signed site acceptance after installation and commissioning checks.
- Fix the warranty trigger. Name the event that starts the warranty, such as site acceptance after a successful SAT or a stated period from delivery or commissioning; FAT release should start it only where that is expressly agreed. A purchase order that links warranty to undefined “acceptance” will be read by each side in its own favour.
- Define re-test rules. The contract should allocate the cost of a re-test and the witness’s re-attendance according to responsibility for the failure.
- Resist deemed-acceptance clauses that treat equipment as accepted a fixed number of days after delivery whether or not a SAT has been run. Acceptance should follow completion of the agreed evidence and tests, not elapsed time alone.
- Hold a retention payment until SAT sign-off. Where the contract provides for it, retention preserves commercial leverage after the equipment has sailed.
FAT payment terms: linking money to the acceptance sequence
Workable FAT payment terms name their evidence. A milestone written as “payment after successful FAT” invites dispute; a milestone written against the signed FAT report and closure of Category A punch items can be invoiced, verified and released without argument.
One workable contracted pattern links a FAT payment to the buyer’s shipment-release decision, retains an agreed amount until SAT sign-off, and starts the warranty from the event named in the contract. Each stage then has money attached to evidence a third party can verify without making the witness the commercial decision-maker.
Frequently asked questions
Does FAT replace pre-shipment inspection?
The FAT records functional checks before packing; the pre-shipment inspection checks the shipment presented for dispatch: quantities against the packing list, closure of punch items, marine packing, preservation and marking, and whether anything was removed or substituted after the test. Equipment may be partially disassembled for transport after the FAT, so the pre-shipment inspection adds a distinct check of the dispatch-ready lot.
Is the SAT the same thing as commissioning?
The SAT and commissioning overlap in time but are different things. Commissioning is the work: energising, loop checks, calibration, trial runs, the activity of bringing installed equipment into operation. The SAT is the verdict: a formal witnessed test against the contractual protocol, run during or at the end of commissioning as the contract sets, whose signature carries only the commercial consequences the contract assigns to it.
Can the FAT checklist be reused as the SAT checklist?
Adapt the FAT checklist structure to the site test protocol. The FAT protocol verifies build and function under factory conditions. The SAT protocol must add what the factory could not test: real utilities, the real process medium, sustained performance at contractual capacity, and integration with the rest of the plant.
What happens if the SAT fails?
The agreed contract and test protocol govern the response, which is why the mechanism should exist before the test. Typical provisions include a punch list for non-critical findings, a re-test for critical ones with cost allocation tied to root cause, and an escalation path if contractual performance cannot be met under site conditions. Responsibility for design, manufacture, programming, documentation, installation, utilities and third-party interfaces follows the contract, the project responsibility matrix and the verified cause. A SAT failure without a contractual mechanism to resolve it is where projects stall.
How Sinospect handles FAT and SAT for China orders
When Sinospect supplies the equipment from China as the principal, the FAT is a gate in its own contract with the manufacturer: the factory’s final balance is released after the agreed evidence meets that gate, not before — the QC-gated payment structure in practice — and Sinospect carries the FAT package through to the site team for the SAT. For buyers who run their own procurement, Sinospect provides independent control on the China side of this chain: reviewing FAT and SAT protocols against the technical file before manufacture begins, witnessing the FAT through factory acceptance testing in China with the authority the buyer defines, controlling the punch list, running the pre-shipment inspection after punch closure, and assembling the documentation package the site team will rely on for commissioning and the SAT. The SAT itself is run at site by the party the contract assigns, with the FAT package as its reference baseline, which is precisely why the factory-side record has to be complete. If you have a live procurement file, an order placed, a FAT approaching, or an acceptance sequence still under negotiation, submit it for review and we will set out what is covered and where the exposure sits.
FAT working resources
Practical resources for this stage, available without an email gate.
Setting up the FAT–SAT sequence for a China order?
Send the equipment scope and where the order stands. Sinospect acknowledges the request within one business day. When the file is sufficient, the initial written assessment follows within two business days with how the FAT and SAT should be split in the contract, the documents to agree with the supplier, how factory-side witnessing would work and a quotation.