Guide
Partial discharge (PD) testing in a factory acceptance test
Last updated
Partial discharge testing is one of the type-specific acceptance tests that sit inside the broader factory acceptance test. For where the FAT fits in the procurement sequence, see the factory acceptance testing guide; for why a test passed in the factory is not the same as one passed on site, see FAT vs SAT. This page covers the PD test specifically: what it reveals, which equipment needs it, how it differs at FAT and SAT, and what a result a buyer can rely on actually records.
What a PD test can reveal that a withstand test does not
Routine withstand tests — the dielectric or “hipot” tests — answer one question: did the insulation survive a defined over-voltage for a defined time. They are pass/fail. They do not reveal incipient weakness: a void, a contaminant, a sharp edge or a delamination that is not yet failing but can degrade in service. Partial discharge is that earlier signal — a discharge that bridges only part of the insulation, measured as apparent charge in picocoulombs (pC) when the conventional IEC 60270 method is used. A unit can pass a withstand test and still show a PD level that indicates elevated insulation risk or a defect that warrants investigation. For high-voltage equipment, where an insulation failure is severe and not visible from the outside until it happens, PD measurement adds evidence of insulation quality that a withstand test alone does not provide.
Which equipment needs a PD test at FAT
PD measurement is not required on every order. It belongs where the equipment is high voltage, an insulation defect is a dominant failure mode, and the product standard or purchaser specification calls for it. Low-voltage equipment, mechanical packages and finished goods generally do not need it. The measurement method and acceptance basis differ by equipment type:
| Equipment | Typical standard | What PD measurement addresses |
|---|---|---|
| Power & distribution transformers | IEC 60076-3 | Voids or contamination in winding and bushing insulation, where the dielectric test sequence includes PD measurement |
| MV/HV switchgear & GIS | IEC 62271-1 plus the applicable part (e.g. 62271-200 for AC metal-enclosed switchgear, 62271-203 for gas-insulated switchgear) | Insulation and assembly defects, and particles in gas-insulated compartments, where the standard requires PD |
| HV cables (manufactured lengths) | IEC 60840 / IEC 62067 | Factory PD test on the produced cable; installed joints and terminations are usually verified at site, where installation workmanship is the main risk |
| Large rotating machines (motors, generators) | IEC 60034-27 series (PD measurement methods and interpretation) | Stator insulation condition, with acceptance criteria taken from the purchaser specification, manufacturer baseline or agreed protocol |
| Instrument transformers & bushings | IEC 61869 (instrument transformers) / IEC 60137 (bushings) | Insulation integrity verification where PD measurement is specified |
Where PD is specified on a transformer order, it is witnessed with the IEC 60076 routine tests and the type and special tests the contract names: see transformer FAT witnessing.
PD at FAT versus PD at SAT
At FAT, PD is measured in the factory or a qualified test laboratory, preferably in a controlled or shielded HV environment with calibrated instruments, a recorded background noise level and a defined voltage profile. This is often the cleanest and most repeatable measurement available before shipment, and the lowest-risk point to reject a defect — while the unit is still on the supplier’s floor and the relevant payment milestone is unmet.
At site, during SAT or commissioning, PD is often re-measured because transport, handling and installation can introduce new defects — though the site noise floor is higher and the measurement is harder. Where PD is specified, a factory PD pass is necessary but not sufficient for final site acceptance: it is the baseline the site result is read against. This is the same gap that separates any factory test from its site counterpart — see FAT vs SAT for why a passed factory test is not a passed site test.
Who provides the PD test equipment?
The PD measuring system is normally provided by the party running the test — the manufacturer’s HV laboratory, or a suitably qualified third-party test laboratory where the manufacturer cannot test to the required level. Sinospect’s role is to specify the PD test in the FAT protocol, arrange it, witness the measurement and control the acceptance record — and, where Sinospect supplies the high-voltage equipment as principal, to treat the PD result as part of the QC gate before the relevant payment milestone is released.
What a credible PD result looks like
A PD result a buyer can rely on records, at minimum:
- the approved ITP or FAT protocol showing PD as a witnessed hold point;
- the standard and method used (e.g. IEC 60270) and the calibration of the PD measuring system, with traceable calibration certificates;
- the test circuit and the applied voltage profile and duration;
- the background or noise level in pC, measured with the test circuit energized so that the test equipment itself is verified not to be generating discharge — a result reported without its noise floor cannot be read;
- the measured apparent charge in pC against the limit set by the applicable product standard, purchaser specification or agreed protocol at the specified voltage;
- the discharge inception and extinction voltages (PDIV / PDEV) where the standard or protocol requires them;
- the serial number and nameplate of the actual unit tested, the test conditions, the laboratory identity and accreditation scope where a third-party lab is used, and the witness signatures with non-conformity disposition if anything failed.
Two red flags recur on China-sourced HV equipment: a “PD: OK” or “pass” line carrying no measured value, noise floor, calibration or test voltage — unless the applicable standard expressly permits a pass/fail statement — and a type-test report substituted where the contract or ITP requires PD evidence on the actual serial-numbered unit.
Frequently asked questions
Is PD testing the same as a hipot or dielectric test?
No. A withstand (hipot) test is a pass/fail check that the insulation survives a defined over-voltage for a defined time; PD testing measures the level of localized discharge inside the insulation. They are usually done together — the unit must withstand the over-voltage and, where specified, keep partial discharge below the limit set by the applicable product standard or specification.
Can I rely on a supplier’s PD report without witnessing it?
With caution. The common gaps are an unstated or improperly measured background noise level, an uncalibrated measuring system, and a report that proves a type unit rather than the serial number being bought. Witnessing the test, or appointing an independent witness, closes those gaps and ties the result to the actual unit.
Does PD need to be re-tested at site?
For critical high-voltage assets it is often specified — especially for installed cable systems, accessories, gas-insulated or site-assembled equipment, or assets exposed to transport and installation risk. The site noise floor is higher and the measurement harder, but the factory PD result is the baseline the site measurement is read against.
What is an acceptable PD level?
There is no universal number. The acceptable level is set by the applicable product standard and/or purchaser specification at the specified voltage and test condition. For transformer dielectric tests, for example, IEC 60076-3 includes partial discharge measurement requirements. The measured value must be read against that limit, with the background noise level below it.
How Sinospect handles PD testing on China orders
When Sinospect is engaged as principal supplier for high-voltage equipment orders that include PD requirements, the PD test is specified in the acceptance protocol and the relevant QC or payment milestone is not released until the unit passes it under witnessed, recorded conditions. When a buyer sources direct, Sinospect provides the same control as a service: specifying the PD test in the factory acceptance test protocol, arranging it in the manufacturer’s HV laboratory or, where needed, a suitably qualified third-party laboratory, witnessing the measurement, and remaining contractually responsible for the agreed test deliverable. Sinospect does not sell PD test instruments; it controls partial discharge as an acceptance event and delivers the witnessed record the buyer, lender or end client relies on. For the working tool the witness applies on the day, see the factory acceptance test checklist. Two services cover the test itself: PD witnessing on transformers and other HV equipment and PD witnessing on switchgear and GIS. If you have a high-voltage order placed or a FAT approaching, submit it for review.
Buying HV equipment from China, or specifying a FAT that should include PD?
Send the equipment scope and the specification. Sinospect responds with whether partial discharge testing applies, how it would be witnessed at the factory, and the evidence the FAT record should carry.
FAT witness in China
USD 730 per day on site for our inspector on simple functional tests under an agreed plan. The plan review, travel and report are added in the quotation: a one-day job is from USD 1,280 all-in. Engineering FATs to our own protocol, and specialist work, are quoted as one fixed price per job.
FAT witness sample report, voltage regulators (PDF)