Guide · Factory acceptance testing
How much does FAT witnessing in China cost?
Last updated
Send your equipment specification, draft test plan and factory city. Sinospect confirms the fixed price and proposed attendee within two business days. Request a fixed-price FAT scope →
USD 730 per day on site for our inspector on simple functional tests under an agreed plan. The plan review, travel and report are added in the quotation: a one-day job is from USD 1,280 all-in. Engineering FATs to our own protocol, and specialist work, are quoted as one fixed price per job. Report format example, packaging line (PDF)
Four ways to staff a China FAT, and what each costs
Buyers commissioning equipment in China choose among four staffing models. Comparing them on the same total-cost basis—before the factory’s test bay is booked—avoids paying day-rate surprises or over-specifying an agency your contract does not require.
Scale: USD 0 to USD 4,300 all-in
Witness day (agreed test plan)
Cost structure: USD 730/day on site · from USD 1,280 all-in
Sinospect’s standard witness-day rate is USD 730 per day on site; plan review, travel in China and the signed report are added in the quotation: a one-day job is from USD 1,280 all-in.
Best when you already have a settled functional test sheet and the factory supplies calibrated instruments.
Engineer-led fixed-price FAT
Cost structure: USD 1,280–4,300 all-in
Sinospect fixed job price, all-in: generators USD 1,280–3,600; switchgear from about USD 1,800; transformers USD 1,800 (1 day), USD 3,050 (2 days) or USD 4,300 (3 days).
Best for power transformers, MV switchgear, generator load-bank runs and custom industrial equipment.
Major TIC agency (SGS, TÜV Rheinland, Bureau Veritas, Intertek)
Cost structure: Quoted per RFQ
No public FAT day rate or fixed job price published on these firms’ own pages (checked on 22 November 2026). Quoted per specification, location and discipline.
Required when the purchase contract or utility names an ISO/IEC 17020 body or vendor-list agency.
Flying your own overseas engineer
Cost structure: Variable (travel + 4–6 workdays)
Return international airfare, visa where required, hotels, domestic transfers in China and four to six workdays away from project engineering.
Fits long multi-week factory runs or design-owner commissioning sign-off where your own team must lead.
To inspect real deliverable and fee formats before requesting a quotation, open our FAT sample report (PDF), scope and fee example, transformer FAT (PDF), or scope and fee example, generator FAT (PDF).
What Sinospect publishes, by equipment and scope
Every Sinospect FAT quotation is confirmed as a fixed total before travel. An all-in quotation covers pre-visit review of the test plan against your specification, our attendee’s site days, travel and lodging in China, calibration checks, measured values, a signed English report within two working days of the last test day on a single-equipment FAT, and one review of the factory’s written responses to open findings.
| Assignment type | Published price | Scope and booking path |
|---|---|---|
| Witness day (simple functional FAT) | USD 730 per day on site for our inspector on simple functional tests under an agreed plan. The plan review, travel and report are added in the quotation: a one-day job is from USD 1,280 all-in. Engineering FATs to our own protocol, and specialist work, are quoted as one fixed price per job. | Agreed functional checklist using the factory’s calibrated instruments. General FAT service. |
| Transformer FAT witnessing | USD 1,800 for one day, USD 3,050 for two, USD 4,300 for three, all-in. | IEC 60076 routine, type and special tests witnessed by our electrical engineer. Quote a transformer FAT. |
| Generator FAT witnessing | USD 1,280–3,600 all-in, as one fixed price per job before you book. | ISO 8528 load-bank steps, power factor, transients, protections and dataplates. Quote a generator FAT. |
| Switchgear & panel FAT witnessing | One fixed price per job, from about USD 1,800 all-in. | IEC 62271 / IEC 61439 construction, wiring, dielectric, interlock and relay checks. Quote a switchgear FAT. |
| Specialist HV, PD, cleanroom & EPC packages | One fixed price per job, built from your test plan. It covers the plan review, attendance, travel in China and the signed report. | Partial-discharge witnessing, cleanroom systems, or multi-factory EPC campaigns. EPC package FAT scope. |
What other inspection firms publish for China FAT
Unlike consumer-goods pre-shipment inspections, industrial FAT witnessing is rarely priced on public rate cards. We checked the own pages of six international inspection firms active in China on 22 November 2026: none of them publishes a FAT day rate or all-in job price online. Every one quotes per request for quotation (RFQ).
| Firm | Service published on its page | Published price | When to choose it |
|---|---|---|---|
| Bureau Veritas | Industrial equipment certification and inspection in China | No price published on its own page on 22 November 2026 (quoted on request) | Contracts naming Bureau Veritas or requiring accredited certification alongside inspection. |
| HQTS | Industrial plants and machinery quality control inspections (FAT witnessing) | No price published on its own page on 22 November 2026 (quoted on request) | General plant and machinery witnessing where you request a project-specific quote. |
| Intertek | Industrial technical inspection services | No price published on its own page on 22 November 2026 (quoted on request) | Projects requiring Intertek on an approved vendor list or tied to Intertek laboratory testing. |
| Pro QC | Global Factory Acceptance Test (FAT) services | No price published on its own page on 22 November 2026 (quoted on request) | Machinery and equipment specification checks quoted against your FAT checklist. |
| SGS | Factory Acceptance Test (SGS China) | No price published on its own page on 22 November 2026 (quoted on request) | Contracts or end-clients that specify SGS by name for factory witnessing. |
| TÜV Rheinland | Factory Acceptance Test (FAT), China | No price published on its own page on 22 November 2026 (quoted on request) | Regulated or utility projects naming TÜV Rheinland or pairing FAT with code certification. |
Flying your own overseas engineer is the fourth option. Instead of a fixed local fee, the real total combines return international airfare, visa fees where applicable, hotels, internal China rail or flights, daily allowances, and four to six workdays of your engineer’s time away from project work. That route pays off on long multi-week commissioning runs or where only your design owner can approve modifications on the shop floor; for a one- to three-day acceptance test, a China-based witness or engineer usually costs less and deploys faster.
Six factors that move a China FAT price
Two quotations for the same nominal equipment can differ widely when one assumes a basic checklist witness and the other prices a multi-day engineering run. Send every firm the same six inputs so the totals stay comparable.
| Cost driver | Why it changes the total | What to settle before booking |
|---|---|---|
| Witness inspector vs discipline engineer | A functional witness checks steps on your already-settled sheet; an electrical or mechanical engineer checks test methods, tolerances and limits under standards such as IEC 60076, IEC 62271 or ISO 8528. | Ask for the proposed attendee’s experience profile before booking. |
| Number of test days and run duration | A single routine functional test finishes in one day; a transformer temperature-rise run, multi-step generator load bank at 0.8 power factor, or multi-panel switchgear programme takes two to three days. | Confirm the factory’s realistic test sequence and hours per day in writing. |
| Factory location and domestic travel | Plants outside major coastal hubs add high-speed rail or domestic flights, local transfers and an overnight hotel stay before or after the test day. | Name the exact factory city in your enquiry so travel is fixed inside the total. |
| Standby days and re-tests when not ready | If the unit, test bay or calibrated instruments are not ready on the scheduled morning, the booked day still runs and a return visit or extra day is needed. | Require a pre-travel readiness check and a written extra-day rate before booking. |
| Specialist measurements and instruments | Partial-discharge testing, high-voltage dielectric witnessing, or cases where our engineer brings calibrated instruments increase preparation and equipment cost. | Clarify which calibrated instruments the factory provides and which the witness brings. |
| Single unit vs batch or multi-factory campaign | Witnessing several units on one visit spreads travel and plan review across the batch, whereas split test dates across multiple factories multiply travel and reporting time. | Group units that can be tested back-to-back in one visit window whenever possible. |
Witness day (USD 730) vs engineer-led FAT: how to decide
Choose the witness day (USD 730 per day on site; plan review, travel and the signed report are added in the quotation: a one-day job is from USD 1,280 all-in) when your test sheet already defines clear pass/fail functional checks, the machine runs standard mechanical or packaging cycles, and the factory supplies calibrated instruments.
Choose an engineer-led fixed-price FAT (from about USD 1,800 all-in for switchgear; USD 1,280–3,600 all-in for generators; USD 1,800 / 3,050 / 4,300 all-in for one-, two- or three-day transformer tests) when the witness must evaluate electrical or thermal readings against standards such as IEC 60076, IEC 62271 or ISO 8528, spot a resistive-only load bank that under-loads an alternator, verify relay settings, or push back on non-conforming test setups on the spot.
If you are unsure which tier fits your machine, send your datasheet and the factory’s draft test sheet. We state in writing whether an inspector witness day suffices or why the job calls for a discipline engineer before you commit.
Five line items to check in every FAT quotation
Before signing any FAT proposal—whether from Sinospect or another inspection firm—ask for written clarity on five items that commonly sit outside a headline day rate:
- Test-plan review before travel. Confirm whether reviewing your specification, drawings and the factory’s draft FAT procedure before the visit is inside the quoted total or billed as extra engineering hours.
- Domestic travel, lodging and local transport. Check whether rail tickets, flights inside China, hotels and taxis are included in one fixed all-in figure or billed later at actuals with a handling margin.
- Standby-day and date-change terms. Factories shift FAT dates frequently. Ask in advance what moving the date costs before travel starts, and what a wasted day costs if the unit is not ready on site.
- Re-inspection or video re-test fee. If a unit fails a test and requires rework, confirm the fee basis for returning to site or witnessing the re-test by live video before you sign the first order.
- Report content and turnaround time. Confirm when the signed report arrives (at Sinospect, within two working days of the last test day on a single-equipment FAT) and whether one review of the factory’s written answers to findings is included.
How Sinospect scopes and delivers a FAT
Sinospect takes standalone FAT witnessing on orders you placed directly with a Chinese manufacturer—you do not need to buy the equipment through us. Send the specification, factory city, target date and draft test plan. Within two business days we send one fixed all-in quotation and the proposed attendee’s experience profile so you can approve both before payment.
Full booking steps, inclusions and equipment scopes are set out on the China FAT witnessing service page.
Related FAT services and resources
Service · Factory acceptance test in China
Full booking terms, deliverables, witness-day and engineering FAT pricing, and sample reports.
OpenService · Transformer FAT witnessing
IEC 60076 routine, type and special test witnessing at Chinese transformer plants (USD 1,800 / 3,050 / 4,300 all-in).
OpenService · Generator FAT witnessing
ISO 8528 load-bank, power-factor, transient and dataplate checks (USD 1,280–3,600 all-in).
OpenService · Switchgear FAT witnessing
Construction, dielectric, interlock and protection checks for MV and LV assemblies (from about USD 1,800 all-in).
OpenResource · Independent FAT attendance
How agenda control, signing authority and structured remote attendance work when you cannot travel.
OpenResource · Factory acceptance test checklist
A 12-section working checklist covering readiness, witnessed tests, measured values and release.
OpenFrequently asked questions
What is the difference between the USD 730 witness day and an all-in FAT price?
USD 730 is Sinospect’s site-day rate for our inspector on simple functional tests under an agreed plan. The quotation adds the plan review, domestic travel and lodging in China, and the signed report: a one-day job is from USD 1,280 all-in. Engineering FATs for transformers, switchgear or generator load-bank testing are quoted from the start as one fixed all-in price per job.
What happens if the factory moves the FAT date or the unit is not ready?
At Sinospect, if the factory moves the date before travel, we rebook at no charge subject to availability on the new date. If our inspector or engineer arrives on site and the unit or test bay is not ready, the booked day stands, we record what we found, and any additional day is quoted to you for approval before anyone stays or returns.
What happens if the equipment fails during the FAT?
The measured non-conformity is recorded in the signed report together with photographs and the factory’s proposed correction. You keep the release decision. Once the factory completes rework, a re-test—either on site or by structured live video if you accept it—is quoted on the same transparent basis.
Will Sinospect’s FAT report satisfy my end-client or a national utility?
On most industrial and EPC orders, a signed independent FAT report with measured values, instrument calibration checks and dated photographs meets the buyer’s contract gate. Where an end-client or national utility contract explicitly requires an ISO/IEC 17020 inspection body or a named agency from its vendor list, appoint that agency directly—Sinospect can still prepare the factory file and pre-check readiness.
How much notice is needed to quote and schedule a FAT in China?
Send the specification, draft test plan, factory city and target test window. Sinospect acknowledges within one business day and provides a fixed-price scope within two business days when the file is sufficient. Booking one to two weeks ahead of the test window gives time to verify test-bay readiness and lock in the right engineer.
Planning a FAT in China?
Send your specification, factory city and draft test plan. We confirm whether a witness day or an engineer-led FAT fits your equipment, with one fixed all-in price before you book.
Sources
Every external firm entry was verified on that firm’s own page on 22 November 2026. Service pages and pricing policies change; check the firm’s current page before relying on it.
Bureau Veritaschecked on 22 November 2026
HQTSchecked on 22 November 2026
Intertekchecked on 22 November 2026
Pro QCchecked on 22 November 2026
SGSchecked on 22 November 2026
TÜV Rheinlandchecked on 22 November 2026
FAT witness in China
USD 730 per day on site for our inspector on simple functional tests under an agreed plan. The plan review, travel and report are added in the quotation: a one-day job is from USD 1,280 all-in. Engineering FATs to our own protocol, and specialist work, are quoted as one fixed price per job.
Report format example, packaging line (PDF)