Skip to content

Tool

Factory acceptance test checklist for mining equipment

Crushers, screens, conveyors, mills and heavy mineral-processing equipment combine high-power drives, structural fabrications and material-handling function, so a factory acceptance test spans build quality, powered performance under load, and the lifting and transport of very heavy assemblies.

Where these most often fall short

The common gaps on heavy mining equipment are undersized or substituted structural steel, drives that run clean unloaded but not at rated duty, and lifting arrangements that were never trial-lifted before the unit was crated.

Refine this checklist

This class comes pre-selected. Untick anything that does not apply to your unit; the universal checks always stay.

Your factory acceptance test checklist

209 checks · 63 critical

Pre-FAT readiness

Always included

Before the test

  • Critical

    Verify a written FAT test plan or inspection and test plan (ITP) exists and has been agreed by buyer and supplier before testing begins.

    Without an agreed plan the pass/fail basis is disputable; testing to an unapproved plan invalidates the acceptance.

  • Major

    Verify the test plan lists each test, its acceptance criteria, the sequence, and the sign-off point for each stage.

    A plan without explicit acceptance criteria per test lets marginal results pass unchallenged.

  • Criticalper your spec

    Verify the current buyer specification, purchase order and approved drawings are on hand at the test location and match the equipment presented.

    Testing against a superseded spec or drawing revision is a common cause of accepted-then-rejected equipment.

  • Majorper your spec

    Verify the revision numbers of the reference documents on the floor are the latest issued and that no open change requests affect the scope under test.

    Uncontrolled or outdated document revisions defeat the purpose of witnessing against them.

  • Criticalper your spec

    Verify the utilities required for the planned tests — electrical supply, compressed air, water, cooling or fuel as applicable — are available and connected at the works.

    Missing or under-rated site utilities routinely stall or truncate a FAT after attendees have travelled.

  • Majorper your spec

    Verify the supplier utility supplies match the values needed by the equipment and the test plan in voltage, frequency, pressure, flow and quality.

    A supply present but at the wrong parameters (e.g. voltage or air pressure) prevents valid performance testing.

  • Major

    Verify the supplier personnel needed to run the test — operators, and the responsible engineer or quality representative — are present and available for the duration.

    Absent competent personnel forces improvised testing or rescheduling; confirm a supplier representative can authorise sign-off.

Safety

  • Critical

    Verify all attendees have received the site safety induction and are issued the required personal protective equipment before entering the test area.

    Un-inducted attendees on a live works floor are a safety and liability exposure and may be removed, halting the FAT.

  • Major

    Verify emergency arrangements for the test area — exits, assembly point, first aid and the site emergency contact — have been briefed to attendees.

    Energised or pressurised acceptance testing carries real hazards; attendees must know the response before it is needed.

Documentation pack

  • Critical

    Verify a valid, in-date calibration certificate is available for every measuring instrument that will be used to judge FAT results.

    Results measured with an uncalibrated or expired instrument are not defensible; check the calibration date has not lapsed.

  • Majorper your spec

    Verify each test instrument's calibration is traceable to a recognised national or international standard and its accuracy is adequate for the tolerances being checked.

    An instrument coarser than the tolerance it verifies cannot confirm conformity; traceability chain should be stated on the certificate.

  • Minor

    Verify blank FAT result sheets or a witness record aligned to the agreed test plan are prepared to log outcomes and signatures as testing proceeds.

    Recording results after the fact from memory weakens the acceptance record; capture readings and sign-offs live.

Deliverable documentation pack

Always included

Documentation pack

  • Major

    Verify a documentation transmittal or index list is provided and that every document it references is physically present in the pack.

    An index with missing referenced items is the most common way an incomplete pack passes unnoticed. Tick each line against a physical document.

  • Critical

    Verify the compiled test and inspection report covering the witnessed FAT results is included, signed and dated by the supplier.

    This is the record the buyer relies on post-shipment. Confirm it is compiled into the pack; the underlying test results are witnessed and judged in the relevant technical modules, not here.

  • Majorper your spec

    Verify material and component certificates required by the purchase order are present, legible and cross-referenced to the items they cover.

    Presence, legibility and traceability into the pack only. Certificate content versus grade/thickness spec is verified in the materials module (mat), not here.

  • Major

    Verify operation and maintenance manuals are included and cover installation, operation, routine maintenance and troubleshooting.

    A common shortfall is an operation-only manual with no maintenance or fault-finding sections.

  • Majorper your spec

    Verify as-built drawings are included and reflect the unit as inspected, including any changes made during manufacture.

    Supplied drawings are frequently the original design set, not as-built. Check revision markings against modifications observed on the unit.

  • Major

    Verify a spare-parts list is included and that each line carries a manufacturer part number sufficient to reorder without further enquiry.

    Descriptions without part numbers, or internal codes the buyer cannot order against, make later replacement dependent on the supplier.

  • Minorper your spec

    Verify recommended commissioning and first-service spares are identified in the spare-parts list and reconciled against what is being shipped with the unit.

    The document side of the spares check. Physical presence of shipped spares in the crates is confirmed in the packing module (pack).

  • Criticalper your spec

    Verify the warranty terms are stated in writing, including duration, start-date basis, coverage and any exclusions or conditions.

    A warranty whose start date, scope or conditions are undefined is difficult to enforce after shipment. Confirm against the purchase order terms.

  • Majorper your spec

    Verify all deliverable documents are provided in the language required by the purchase order.

    Manuals or certificates supplied only in Chinese are a frequent finding. Confirm the required language, and whether bilingual or translated copies were agreed.

  • Major

    Verify the equipment nameplate details recorded in the documents (model, serial number, rating) match the physical nameplate on the unit.

    Documents describing a different serial or rating than the unit indicate a mismatched or reused pack.

  • Minor

    Verify supplier and sub-supplier contact details for technical support, spares and warranty claims are stated in the pack.

    Post-shipment support stalls when the buyer has no named contact route for parts or warranty.

  • Minor

    Verify each document carries a title, revision or issue identifier and date so the buyer can confirm they hold the current edition.

    Unversioned documents make it impossible to tell later whether a superseded copy is in use.

Common failure modes

  • Majorper your spec

    Confirm the pack is specific to this unit rather than a generic product-family manual that omits ordered options or variants.

    Generic manuals are commonly substituted for a bespoke build; they describe standard options and omit or contradict what was actually supplied.

  • Minorper your spec

    Confirm that where an electronic pack is provided, the files open, are complete and are not password-locked or corrupted, and that any promised native formats are included.

    A USB or link handed over at FAT can hold scanned-only, locked or incomplete files. Open a sample and confirm agreed formats (e.g. editable drawings) are present.

Packing & pre-shipment readiness

Always included

Before the test

  • Minorper your spec

    Confirm the packing specification (or packing list) and the intended transit mode and route are available before packing is inspected.

    The packing method must be judged against the declared mode (sea/air/road, container vs breakbulk) and destination; without the spec the packing cannot be assessed.

Build & dimensional

  • Majorper your spec

    Verify the packing method and materials match the specification for the declared transit mode (seaworthy export crate, container-stuffed, or air freight as applicable).

    Domestic-grade packing on a long sea leg is a common failure; export/seaworthy protection is often specified but substituted to save cost.

  • Major

    Inspect crate and case construction for adequacy — base skids/runners, bracing, fixings and closure — so the package will withstand handling and stacking in transit.

    Judge build quality only; lifting points, slinging arrangements and tilt/shock indicators are assessed under the lifting & transport module.

  • Majorper your spec

    Verify shipping marks on each package (consignee, order/contract reference, case number, port of destination) match the packing list and commercial invoice.

    Mismarked cases are misrouted or delayed at consolidation; case-number sequence must be complete (e.g. 1/8 … 8/8).

  • Majorper your spec

    Verify the gross and net weights and outer dimensions marked on each package agree with the packing list.

    Declared weights drive freight booking, container/vehicle selection and handling gear; discrepancies cause re-handling and demurrage.

  • Minor

    Verify handling and orientation markings (e.g. this-way-up, keep-dry, sling/no-sling positions, fragile) are present and correct for the contents.

    ISO 780 pictograms are conventional; confirm they are present and consistent with the packing spec rather than citing the standard on the case.

  • Majorper your spec

    Verify all loose-supplied items — spares, consumables, special tools, counterparts and accessories — listed in the contract/packing list are physically present and identified.

    Loose supply is the most common short-shipment; missing commissioning spares or special tools can stall installation at site.

  • Majorper your spec

    Where preservation is specified, verify it is applied — desiccant with a humidity indicator in sealed barrier/VCI wrapping, VCI on bare machined surfaces, and blanking of open ports, flanges and shaft ends.

    Long sea transit and storage cause corrosion on unprotected surfaces; desiccant quantity and a moisture-barrier seal are routinely skimped.

  • Majorper your spec

    Verify fluids are handled per the shipping requirement — systems drained or protective/preservation fill applied and stated, with drain points closed and no residual leakage.

    Trapped water can freeze or corrode in transit; some units ship with a preservation charge that must be documented so site does not re-drain it.

Documentation pack

  • CriticalISPM-15

    Verify wooden packaging carries a valid ISPM-15 heat-treatment (HT) or fumigation mark with the producer's registration.

    Unmarked or non-compliant timber is refused or destroyed at the destination port and can hold the whole consignment; applies to all solid-wood packaging.

  • Criticalper your spec

    Verify the equipment serial/tag number, model and quantity match the nameplate, the packing list and the commercial invoice.

    Serial-number mismatch between the physical unit and the shipping/commercial documents is a fraud and customs-clearance exposure and can invalidate warranty.

Common failure modes

  • Major

    Witness and obtain a dated photographic record of each unit as packed — internal blocking/bracing and preservation before closing, then the closed and marked package.

    Once crates are closed the internal packing cannot be re-inspected; before-close photos are the only evidence for transit-damage and short-shipment claims.

Material identity and fabrication quality

Before the test

  • MajorEN 10204

    Verify the material certificate pack is complete: one mill test certificate (MTC/MTR) is present for every grade of pressure- and load-bearing material used in the build, and each certificate is legible and traceable to a heat/cast number.

    Confirm certificate type meets the PO requirement (e.g. EN 10204 3.1 with an independent 3.2 where the contract calls for one). A pack that is incomplete before the FAT usually stays incomplete after payment.

  • Major

    Verify a material traceability list (heat-number map) is available that ties each major fabricated component to the heat/cast number and certificate covering its material.

    Without a component-to-heat map, heat-number trace-back on the floor is guesswork. Its absence is itself a finding.

  • Major

    Verify a working positive material identification (PMI) analyser (portable XRF or OES) with valid calibration and a certified reference sample is available for use during the FAT.

    Check the analyser reads the reference sample correctly before trusting any part result. If no analyser is available, record that alloy grade could not be independently confirmed — do not sign it off from paperwork.

Build & dimensional

  • Majorper your spec

    Cross-check each mill test certificate against the specified material: confirm grade/designation, and the certified chemical composition and mechanical properties (yield, tensile, elongation, and impact/Charpy where required) fall within the specified grade's limits.

    A certificate that lists an equivalent-but-different grade, or that omits a required impact test, is a specification non-conformity even when the paperwork looks in order.

  • Criticalper your spec

    Perform a PMI analyser spot-check on a sample of parent material across the major fabricated components and confirm the measured alloy composition matches the grade claimed on the corresponding certificate.

    This is the primary defence against grade substitution — e.g. carbon steel supplied where a low-alloy or stainless grade was specified, or a lower stainless grade (304) substituted for a higher one (316). Paper review cannot detect this. Sample coverage should follow an agreed plan; witness every reading yourself.

  • Critical

    Trace heat/cast numbers back from the physical steel to the certificates: locate the hard-stamp or paint marking on a sample of components and confirm each traces to a heat number listed on a certificate in the pack.

    Material with no transferable identity, or bearing a heat number not present in the certificate pack, cannot be shown to be the certified material. Watch for over-stamping or re-stamping of heat numbers.

  • Majorper your spec

    Measure the thickness of key plate and the wall thickness / section size of key structural or pressure members and confirm they meet the specified nominal dimension and material tolerance.

    Under-thickness plate or lighter sections than specified is a common cost-down substitution. Measure at several points; use ultrasonic thickness gauging where a face is inaccessible.

  • Majorper your spec

    Measure the principal dimensions of key machined or fabricated components (bores, mating faces, hole patterns, critical lengths) and confirm they are within the tolerances stated on the component drawings.

    Component-level dimensional conformity only; overall assembly conformance against the general-arrangement drawing is verified elsewhere.

  • Major

    Visually inspect a representative sample of welds for workmanship: confirm consistent profile and full fill, and freedom from undercut, overlap, visible cracks, unfilled craters, porosity clusters, arc strikes and excessive spatter.

    Visual weld quality only. Weld conformance to a weld map, and non-destructive-examination records for pressure parts, are verified in their own modules and are not repeated here. Use a weld gauge for undercut/reinforcement where acceptance limits apply.

  • Minor

    Visually inspect the applied coating/paint finish for continuity and workmanship: confirm even coverage with no runs, sags, blistering, dry spray, missed areas or exposed substrate, and confirm adhesion is sound at a spot check.

    Visual coating quality only. Dry-film-thickness measurement against a coating specification is verified in the relevant structural / envelope module and is not duplicated here.

  • Criticalper your specISO 898-1

    Inspect installed fasteners for grade and authenticity: confirm bolt heads carry the correct property-class marking and a manufacturer identification mark, threads and plating are clean and undamaged, and there is no sign of re-stamped, ground-off or mismatched head markings.

    Counterfeit and substandard fasteners are widespread. Warning signs: blank heads on structural bolts, absent or inconsistent manufacturer marks, over-stamped grade markings, poor thread finish, and grade markings that do not match the specification (e.g. 4.8 marked or supplied where 8.8/10.9 is required). Stainless grade marking (A2/A4) applies where corrosion-resistant fasteners are specified.

  • Majorper your spec

    On critical bolting, spot-check fastener authenticity by hardness test or PMI where feasible, and confirm the result is consistent with the marked property class or specified fastener material.

    Head markings can be forged; a hardness or alloy check on a sample confirms the fastener is what it is stamped to be. Restrict to structural, pressure-retaining or safety-critical bolting.

Documentation pack

  • Minor

    Collect copies of the mill test certificates, the PMI spot-check report (readings with instrument and reference details), fastener certificates or conformity declarations, and any coating/paint application records generated for this equipment.

    The PMI report and heat-map are the objective evidence that identity was verified, not merely certified. Retain them with the FAT pack.

Common failure modes

  • Criticalper your spec

    Confirm no component carries a heat number that is absent from the certificate pack, and no supplied grade is a downward substitution of the specified grade justified only as an 'equivalent'.

    Grade substitution and untraceable heats are the highest-consequence material fraud at FAT: they pass a paper review and only surface in service. Treat any mismatch between analyser, stamp and certificate as a hold point, not a documentation nit.

Electrical power

Before the test

  • Criticalper your spec

    Confirm the equipment's rated supply (voltage, phases, frequency) on the nameplate matches the buyer's site supply and purchase order before any powered test.

    A mismatch (e.g. 400 V/50 Hz build against a 480 V/60 Hz site) renders the unit uninstallable and can destroy it on first energisation.

  • Majorper your spec

    Verify the current, dated approved schematic and panel-layout drawings are present at the FAT and match the drawing revisions on the buyer's order.

    All build-versus-schematic checks are only as good as the drawing revision witnessed against; a superseded revision invalidates the comparison.

Build & dimensional

  • Majorper your spec

    Compare the as-built panel against the approved schematic: device ratings, part numbers, contactors, breakers, fuses and cable cross-sections match the drawing and bill of materials.

    Substituted or under-rated components are a common cost-cutting deviation and are hard to detect after the panel is closed and shipped.

  • Major

    Inspect conductor terminations for correct lugs/ferrules, no stray strands, no exposed copper beyond the terminal, and no damaged insulation.

    Poor terminations cause loose connections, arcing and hot spots that appear only under load in service.

  • Majorper your spec

    Witness torque verification on a sample of power terminals and busbar joints using a calibrated torque tool against the manufacturer's stated values, and confirm tightness-check marking is applied.

    Under-torqued power connections are a leading cause of in-service overheating; over-torqued terminals crack. Torque values are device-specific.

  • Minor

    Verify cable and conductor identification (wire numbers, phase colours, ferrules) is present, legible and agrees with the schematic wire numbering.

    Missing or wrong wire numbers make site fault-finding and reconnection after shipment slow and error-prone.

  • Minorper your spec

    Confirm cabinet and device rating, warning and identification labels (main switch, incoming supply, danger/voltage warnings, panel schedule) are fitted, in the agreed language, and durable.

    Language and label content are order-dependent; absent voltage-warning labels are also a safety and acceptance issue at site.

Functional tests

  • Criticalper your spec

    Witness protective-earth (PE) and equipotential-bonding continuity from the main earth terminal to accessible exposed conductive parts (panel door, frame, motor bodies, enclosures).

    Pass: Continuity confirmed with low measured resistance (typically ≤ 0.1 Ω, or the value stated in the buyer's spec/applicable standard) at each point tested.

    Broken bonding leaves accessible metalwork live under an insulation fault. The pass threshold varies by standard and conductor length; confirm the value used.

  • Criticalper your spec

    Witness an insulation-resistance (IR) test on the de-energised power circuits at the appropriate test voltage, with electronics/sensitive devices disconnected or protected as required.

    Pass: IR meets or exceeds the minimum stated in the buyer's spec or applicable standard for the circuit voltage (commonly ≥ 1 MΩ, with higher acceptance values typical for LV installations); no circuit fails.

    Low IR indicates damaged, damp or pinched insulation and a shock/short risk. Acceptance value is voltage- and standard-dependent; verify the applied test voltage suits the equipment.

  • Majorper your spec

    Witness a powered check of motor/drive rotation direction for each driven unit and confirm it matches the direction arrow and process requirement.

    Pass: Observed rotation matches the marked direction arrow and the buyer's specified process direction for every motor tested.

    Reversed phase sequence spins pumps, fans and conveyors backwards; on some equipment reverse running causes immediate damage. This is direction only — mechanical rotating-machinery checks are covered separately.

  • Majorper your spec

    Verify overload and thermal-protection settings on motor starters and drives are set to the connected motor's full-load current and to the values on the coordination/settings documentation.

    Pass: Each overload/thermal setting matches the motor full-load current and the documented setpoint; no device left at an arbitrary default.

    Overloads left at maximum default provide no motor protection; set too low they nuisance-trip on start.

Safety

  • Criticalper your spec

    Confirm protective-device ratings and settings (main breaker, branch breakers, fuses, RCD/earth-fault where fitted) agree with the protection-coordination study or discrimination documentation supplied with the equipment.

    Devices that do not match the coordination study can fail to clear a fault or trip out of sequence. This verifies protective settings against the design documents, not control logic.

  • Majorper your spec

    Verify IP-rated enclosure integrity for electrical parts: gland plates fitted, unused entries blanked, no open knockouts, and doors/covers close on intact seals.

    Open entries defeat the enclosure's ingress rating and expose live parts to dust, moisture and contact. Required IP rating is order-dependent.

Documentation pack

  • Major

    Collect the completed electrical test records — insulation-resistance readings, earth/bonding continuity results, and torque-check sign-off — with the tester's identity and instrument details noted.

    The signed record is the shipment-payment evidence that these safety-critical tests were actually performed and passed.

  • Minor

    Collect valid calibration certificates for the insulation tester, earth-continuity/loop tester and torque tool used during the electrical tests.

    Readings from out-of-calibration instruments are not defensible; expired calibration undermines the whole electrical test record.

Common failure modes

  • Critical

    Sample-check that internal wiring is not left connected to an incorrect phase or omitted where the schematic shows all three phases loaded, and that neutral and earth are not interchanged at terminals.

    Neutral/earth swaps and dropped phases pass a quick visual and even a rotation check yet create a shock hazard and unbalanced loading; they surface only under systematic point-to-point verification.

Rotating machinery

Before the test

  • Majorper your spec

    Confirm the unit is fully assembled on its baseplate or skid as it will ship, with bearings lubricated to the specified grade and level, before any run test.

    A run test on a partially built or dry-bearing unit is not representative and can damage bearings.

  • Majorper your spec

    Verify the driven speed to be used for the run test matches the rated duty speed on the datasheet or purchase order.

    Vibration, balance, and bearing temperatures are only meaningful when taken at the intended operating speed.

Build & dimensional

  • Majorper your spec

    Verify shaft end runout with a dial indicator and confirm it is within the manufacturer's stated tolerance.

    Pass: Total indicated runout at or below the manufacturer's stated limit for the shaft.

    Excess runout indicates a bent shaft or poor machining and drives vibration once running.

  • Majorper your spec

    Verify shaft-to-shaft alignment across the coupling (angular and parallel offset) and record the as-left values.

    Pass: Angular and parallel misalignment within the coupling manufacturer's or datasheet tolerance for the operating speed.

    Alignment set at the works can shift in transit, but an out-of-tolerance as-left value is a build defect that must be corrected before shipment.

  • Majorper your spec

    Verify the coupling is the specified type and size, correctly fitted, and that any flexible element or spacer is present and undamaged.

    A substituted or wrongly sized coupling transmits misalignment loads and shortens bearing life.

  • Minor

    Verify hold-down bolts and the presence of shims under feet, and check for soft foot at each mounting point.

    Uncorrected soft foot distorts the machine frame and produces alignment and vibration that reappear after re-tightening on site.

Functional tests

  • Majorper your spec

    Witness an uninterrupted run at duty speed for the agreed duration and confirm no abnormal noise, knocking, rubbing, or intermittent contact is heard or felt.

    Pass: Machine runs continuously for the agreed run-in period with no audible or tactile signs of internal contact, looseness, or distress.

    General mechanical distress check only; sound-level measurement against a limit is out of scope for this module.

  • Majorper your spec

    Measure broadband vibration at each accessible bearing housing (horizontal, vertical, and axial) while running at duty speed and record the values.

    Pass: Measured vibration velocity at every measurement point at or below the acceptance limit stated on the datasheet, purchase order, or the referenced vibration standard.

    Acceptance grade depends on machine class and mounting; confirm which limit applies before witnessing. ISO 10816/20816 series is commonly cited but only reference it if the datasheet does.

  • Majorper your spec

    Where residual unbalance is a datasheet requirement, witness or review the rotor balancing record and confirm the achieved balance grade meets specification.

    Pass: Balance grade recorded for the rotor meets or exceeds the grade required by the datasheet or purchase order.

    ISO 21940 (formerly ISO 1940) covers balance grades but only cite it if the specification does; otherwise verify against the stated grade.

  • Majorper your spec

    Run the unit until bearing temperatures stabilise and record the stabilised temperature at each bearing.

    Pass: Each bearing temperature reaches a steady value (no continuing rise) at or below the manufacturer's stated maximum for the bearing type.

    A bearing that keeps climbing or stabilises above its limit signals over-lubrication, misalignment, preload, or a bearing fault.

Safety

  • Critical

    Verify that fixed guards enclose all exposed rotating parts — coupling, shaft ends, keys, belts, and pulleys — and are securely fixed with the correct fasteners.

    Exposed rotating parts are a direct entanglement hazard; physical guard fitment is checked here, whereas any guard interlock function is verified under the safety-systems module.

Documentation pack

  • Minor

    Collect the signed test records for shaft alignment, vibration readings, and stabilised bearing temperatures, and any rotor balancing certificate.

    These as-left values are the site baseline for commissioning and later condition monitoring.

Common failure modes

  • Major

    Confirm the coupling guard has adequate running clearance and shows no witness marks or contact with the rotating coupling during the run.

    A guard fitted too close to the coupling can foul it in service; rub marks after the run reveal insufficient clearance.

  • Major

    After the run test, re-check that bearing housing, coupling, and hold-down fasteners have not loosened and that no lubricant weeping is visible at bearing seals.

    Fasteners that back off during the first run and leaking seals are common early-life failures that surface only after running under load.

Hydraulic and pneumatic power systems

Before the test

  • Majorper your spec

    Verify the system is charged with the specified fluid and grade and filled to the correct level, and that the reservoir breather and any sight glass are fitted and clear.

    Wrong fluid grade or an under-filled reservoir invalidates hold and function tests. The specified fluid is buyer/PO-dependent.

  • Major

    Confirm the pressure gauge or transducer used to record the hold and relief tests carries valid, in-date calibration.

    A prerequisite for this module's own pressure readings. General instrument-calibration verification is owned by the instrumentation module; this item only guards the gauge relied on for the tests below.

Build & dimensional

  • Criticalper your spec

    Verify every flexible hose bears a legible marking showing its maximum working-pressure rating and that the rating meets or exceeds the maximum system pressure for its circuit.

    An under-rated or unmarked hose is a burst and whip hazard. The required rating derives from the circuit's rated pressure.

  • Major

    Inspect hose and tube routing for adequate bend radius, protection against chafe at every contact point, clearance from hot or moving parts, and secure clamping with no unsupported spans.

    Chafe and tight bends are the leading cause of in-service hose failure; catch routing defects before shipment while access is easy.

  • Major

    Verify fittings, unions and manifold ports are of the correct type and correctly torqued, with no thread-tape or sealant migration into the flow path and no mixing of incompatible fitting standards.

    Mixed thread standards and sealant debris are common on China-built power packs; both cause leaks or contamination.

Functional tests

  • Criticalper your spec

    Run the circuit up to maximum rated working pressure, isolate the pressure source, and record pressure decay over a defined hold period.

    Pass: Pressure decay over the specified hold period stays within the buyer's or manufacturer's stated tolerance; where none is stated, the circuit holds with no visible drop attributable to internal or external leakage over a minimum 10-minute hold.

    The core integrity test. Hold period and allowable decay are spec-dependent; agree them with the manufacturer before the test.

  • Critical

    With the circuit held at maximum rated working pressure, inspect every joint, seal, cylinder rod gland, fitting and hose end for external leakage.

    Pass: No external leakage at rated pressure — no drips, no weeping film that reforms after wiping, and no audible air leak on pneumatic circuits.

    Distinguish residual assembly oil from an active leak by wiping dry and re-observing under pressure.

  • Majorper your spec

    Cycle each cylinder or actuator through its full stroke in both directions under normal operating pressure and observe travel, seating at both ends, and rod-surface condition.

    Pass: Each actuator completes full rated stroke in both directions and seats fully at both ends, with smooth motion free of stiction, judder or stall, and no scoring, pitting or plating damage visible on the rod.

    Full-stroke travel is buyer/drawing-dependent. Rod damage and stiction predict early seal failure. Cylinder function only — control-logic and interlock response is owned by the controls module.

  • Criticalper your spec

    Witness the setting of each circuit relief or pressure-limiting valve and confirm it relieves at its intended set point, protecting the circuit against over-pressure.

    Pass: Each relief valve cracks and fully relieves at its set point within the specified tolerance, and system pressure does not exceed the rated maximum when the valve operates.

    Circuit protection for the hydraulic/pneumatic power system. Set points are spec-dependent. Code relief valves on pressure vessels are witnessed under the pressure-bearing module, not here.

  • Majorper your spec

    Where the circuit uses accumulators, verify the pre-charge gas pressure against the specified value and confirm it holds.

    Pass: Measured pre-charge equals the specified value within tolerance and holds steady over a short observation with the circuit isolated.

    Incorrect pre-charge causes erratic function and premature bladder failure. Applies only where accumulators are fitted; pre-charge value is spec-dependent.

  • Majorper your spec

    Verify the hydraulic fluid cleanliness class against the specified target, by sampling and analysis or by particle count, and confirm return-line and pressure-filter elements are of the specified rating and correctly installed.

    Pass: Measured cleanliness class meets or is cleaner than the specified target; filter element ratings match the specification and elements are seated with any clogging indicator reading normal.

    Cleanliness class is buyer/spec-dependent and typically stated on the ISO 4406 scale; do not assume a value the buyer has not specified. Contaminated fluid at handover destroys valves and pumps in service.

Safety

  • Critical

    Verify the circuit can be isolated and its stored energy safely released — accumulators bled down and residual pressure vented — and that a means of isolation and depressurisation is provided and identified.

    Stored hydraulic pressure and charged accumulators are a stored-energy hazard specific to fluid power. Guard interlocks and e-stops are covered by the safety-systems module; this item is the fluid-power isolation and bleed-down provision.

Documentation pack

  • Minor

    Collect the hydraulic and pneumatic circuit schematic and confirm it identifies components, set points and port markings consistent with the as-built system.

    A schematic that does not match the as-built circuit blocks commissioning and fault-finding on site.

  • Minor

    Collect records of the pressure-hold, relief-valve set-point and fluid-cleanliness results, with component data sheets and any accumulator pre-charge record.

    These records substantiate the witnessed tests and are needed for the acceptance file.

Common failure modes

  • Major

    Confirm no temporary flushing hoses, jumpers or blanking plugs remain in the circuit and that all commissioning bypasses have been removed before the acceptance run.

    Flushing loops and blanking plugs left in place after commissioning are a recurring cause of leaks and misfunction on first site start-up.

Controls, PLC and HMI

Before the test

  • Criticalper your spec

    Verify the current I/O list, control narrative or functional design specification, interlock (cause-and-effect) schedule and alarm list are on hand and match the equipment presented.

    These are the reference documents every control test is judged against; without them I/O and logic outcomes cannot be declared conforming.

  • Majorper your spec

    Verify the PLC/HMI program loaded on the equipment is the revision agreed for FAT and record its version, checksum or download date against the control documentation.

    Testing an undocumented or superseded program means the witnessed behaviour may not match what ships; capture the identifier now so later changes are detectable.

Build & dimensional

  • Minorper your spec

    Verify HMI screen tag names, labels, symbols and page navigation are consistent with the I/O list and control narrative, with no placeholder, mislabelled or orphaned objects.

    Mismatched or leftover tags mislead the operator and often signal an incomplete or copied-from-another-project screen build.

Functional tests

  • Criticalper your spec

    Witness a point-to-point I/O check: force or actuate each input and output in turn and confirm it maps to the correct address, tag and HMI indication per the I/O list.

    Pass: Every I/O point exercised corresponds to the address, tag and description on the I/O list, with the expected HMI state change and correct polarity (no swapped, inverted or dead points).

    Crossed, inverted or unterminated I/O is the most common controls defect and can drive the wrong actuator on site; this checks the wiring-to-logic-to-screen chain, not sensor accuracy.

  • Criticalper your spec

    Witness each safety and process interlock and permissive by simulating its trip condition, and confirm the control system inhibits or halts the affected function and reports the cause.

    Pass: Each interlock and permissive in the cause-and-effect schedule, when its condition is simulated, produces the specified control action (block start, stop, hold or trip) and the correct annunciation; none can be bypassed from the operator interface without the defined authorisation.

    Interlocks are the logic that protects the equipment and operators; each branch of the cause-and-effect matrix must be proven individually, not assumed from a single successful run.

  • Majorper your spec

    Witness alarm generation for a representative set of alarm conditions and confirm each raises, displays, time-stamps, acknowledges and clears correctly through the alarm list.

    Pass: Each simulated condition raises the corresponding alarm at its configured setpoint with correct text, priority and time stamp; acknowledgement and return-to-normal behave per the alarm specification, and no alarm is stuck, duplicated or missing.

    Alarms are the operator's window onto faults; wrong priority, missing text or an alarm that will not clear undermines fault response on site.

  • Majorper your spec

    Verify the HMI display language, engineering units, number formats and time zone/clock are set as specified, and that the language set the buyer will operate in is complete on every screen.

    Pass: All HMI text, alarms and prompts display in the specified language(s) with the specified units (e.g. metric/imperial) and formats; no screen reverts to the default factory language or shows untranslated or unit-mismatched fields.

    Screens left in the manufacturer's default language or in the wrong units are a frequent and operationally serious miss for export equipment.

  • Majorper your spec

    Witness operation through each control mode and operator command the equipment provides — such as manual/auto, start/stop, and any sequence or step control — and confirm the control system responds as described in the control narrative.

    Pass: Each mode selection and command produces the response defined in the control narrative, transitions between modes are handled safely, and invalid commands are rejected or ignored rather than causing undefined behaviour.

    Mode and sequence handling is where control logic gaps surface; confirm the documented behaviour, not just that the equipment moves.

  • Majorper your spec

    Witness a demonstrated data exchange with each third-party or external system the control system must communicate with — such as a plant SCADA, upstream/downstream PLC or supervisory network — over the specified protocol.

    Pass: For each specified interface the link establishes over the agreed protocol and address, representative signals are read and written correctly in both directions, and a communication loss is detected and annunciated by the control system.

    Comms to other systems are hard to fix after shipment; confirm the actual mapped exchange and the loss-of-comms response, not merely that a cable is connected. If the counterpart system is unavailable at the works, record what could and could not be demonstrated.

Safety

  • Criticalper your spec

    Witness activation of each emergency stop through the control system and confirm the controller registers the stop, commands the outputs to their defined safe state, and annunciates the e-stop condition.

    Pass: On each e-stop actuation the control system drives all outputs to the specified safe state, prevents restart until the e-stop is reset and the defined reset/acknowledge sequence is completed, and displays the e-stop as active.

    This checks the control system's response to and annunciation of an e-stop and the inhibited restart; integrity of the hardwired safety circuit and stored-energy isolation is verified under the safety-systems module.

Documentation pack

  • Major

    Collect the as-tested I/O list, interlock/cause-and-effect schedule and alarm list, marked up with the FAT witness results and any changes made during testing.

    The marked-up control documents are the record of what was actually proven and the baseline for site commissioning; undocumented in-test changes are a frequent source of later disputes.

Common failure modes

  • Critical

    Verify no I/O points, interlocks or alarms remain forced, overridden, bypassed or disabled at the end of testing, and that any forces used during the FAT have been removed.

    Forces applied for testing that are left in place ship a controller that ignores real inputs or defeated interlocks; confirm the force/override table is clear before sign-off.

  • Major

    Verify that signals presented as satisfied during interlock and functional tests are driven by genuine field conditions or agreed simulation, and confirm which inputs were physically actuated versus simulated in software.

    A logic branch can appear to pass while the input is merely simulated in the program; record the method so simulated-only results are not mistaken for a proven physical response.

Structural and load-bearing fabrications

Before the test

  • Majorper your spec

    Verify the approved general-arrangement and structural fabrication drawings, the weld map, and the specified coating system are on hand and match the revision on the item presented.

    The structural checks below are meaningless without the governing drawing and weld map at the correct revision to check against.

Build & dimensional

  • Majorper your spec

    Measure the principal overall dimensions of the structure — length, width, height and diagonals — and confirm they fall within the tolerances stated on the general-arrangement drawing.

    Out-of-tolerance overall dimensions cause interference or gaps at the installation interface; diagonals reveal out-of-square that single edges hide.

  • Majorper your spec

    Verify the structure is square and plumb, checking frame diagonals and the verticality of columns or uprights against the drawing.

    A racked or leaning frame loads members eccentrically and misaligns mounted equipment even when individual dimensions pass.

  • Majorper your spec

    Verify member sizes, section profiles and plate thicknesses at load-bearing locations match the sizes called up on the fabrication drawing.

    Substitution of a lighter section or thinner plate than specified reduces load capacity and is not visible without measurement against the drawing.

  • Majorper your spec

    Verify the mounting interfaces for equipment carried by the structure — hole patterns, pitch, bolt-circle and bearing faces — match the interface drawing.

    A structure that is correct in isolation but whose mounting pattern does not match the equipment it supports cannot be assembled on site.

  • Criticalper your spec

    Verify that every weld shown on the weld map is present at its indicated location, with the specified type, length and leg or throat size, and none are omitted.

    Weld completeness against the map is dimensional coverage, not metallurgical quality; a missing or undersized structural weld is a load-path defect. Weld metallurgy, procedure and NDT belong to the materials and fabrication-quality checks.

  • Majorper your spec

    Perform a visual examination of structural welds against the visual acceptance criteria stated on the drawing, checking profile, undercut, overlap, surface porosity and unfilled craters.

    This is the drawing's stated visual acceptance check, distinct from NDT and weld-procedure verification which are covered by the materials and fabrication-quality module.

  • Majorper your spec

    Verify the base or footprint of the structure is flat within the stated tolerance so it will seat on the foundation without rocking or forced shimming.

    A base out of flat transmits distortion into the structure when bolted down and can pre-load members or crack grout; measure across the full footprint.

  • Criticalper your spec

    Verify the anchor or holding-down hole pattern — hole positions, diameters, slot orientation and edge distances — matches the foundation or interface drawing.

    An anchor pattern that does not match the cast-in bolts or foundation renders the unit uninstallable; a very common and costly on-site discovery.

  • Majorper your spec

    Verify field-bolted structural connections use the fastener grade, size and count shown on the drawing and that faying surfaces are prepared as specified.

    Confirms the connection as built matches the drawing arrangement; fastener certification, traceability and material grade verification belong to the materials module.

  • Majorper your spec

    Measure the dry-film thickness of the applied coating at representative points and confirm it meets the minimum specified for the coating system.

    Pass: Dry-film thickness readings meet or exceed the specified minimum across the sampled points, within the acceptance rule stated for the coating system.

    Under-thickness coating shortens the corrosion life of the structure; surface preparation grade, coating material identity and coating quality belong to the materials and fabrication-quality module — this item verifies applied film thickness only.

Functional tests

  • Criticalper your spec

    Witness a static load test of the structure at the test load defined in the specification and measure the deflection at the specified point during and after the load is applied.

    Pass: Measured deflection under the applied test load does not exceed the limit stated in the specification, and the recovered (permanent) deflection after the load is removed is within the stated allowance, with no visible yielding, buckling or weld cracking.

    A structure can pass every dimensional check yet deflect excessively or take a permanent set under load; the test load and deflection limit must come from the buyer's specification, not be assumed.

Documentation pack

  • Minor

    Collect the dimensional and squareness inspection record, the weld visual and completeness report against the weld map, the load-test record with measured deflections, and the coating dry-film-thickness readings.

    These records evidence the structure was verified as built and are needed for the acceptance file and any later warranty claim.

Common failure modes

  • Criticalper your spec

    Check that no structural weld shown on the map has been substituted with tack welds, intermittent welds where continuous is specified, or filler applied only to conceal a gap.

    A frequent cost-cutting or fit-up shortcut: welds that look complete at a glance but are tacked, stitched or cosmetic, leaving the load path incomplete. Verify against the weld map, not appearance alone.

  • Majorper your spec

    Check that packing plates, added gussets or shims have not been introduced to make an out-of-tolerance structure appear dimensionally correct at the interfaces.

    Unplanned packing to force a mating dimension masks a fabrication error and can leave an eccentric or unsupported load path once installed.

Load-handling equipment

Before the test

  • Criticalper your spec

    Verify the rated capacity, duty classification and applicable overload test factor to be applied are stated in the purchase order or the equipment specification before load testing begins.

    The overload percentage varies by equipment type and governing code; witnessing an overload test to an unstated or assumed factor makes the result unusable. Fix the declared factor first.

  • Major

    Verify the certified test weights or calibrated load cell to be used give a load value traceable and adequate to prove the rated and overload conditions.

    A load applied through an uncertified weight or an uncalibrated cell cannot substantiate the capacity claim. Calibration validity of the reference instrument itself is covered under instrumentation (inst).

Build & dimensional

  • Criticalper your spec

    Verify the safe working load or rated capacity is durably and legibly marked on the equipment where the operator can read it, and matches the ordered rating.

    Unmarked or wrongly marked capacity is both a legal defect and an in-service overload hazard. Confirm the figure against the purchase order, not just its presence.

  • Majorper your spec

    Verify the load-bearing rope, chain, sling or belt is the specified type and size, is correctly reeved or tracked, and shows no manufacturing defect, kinking or damage.

    Incorrect reeving or an under-size rope or chain undermines the rated capacity regardless of a passed load test. Structural members and welds of the frame are assessed under the structural module (struct).

Functional tests

  • Criticalper your spec

    Witness a lift, hold and lower of the rated capacity through the working range and observe the load-handling movements complete without abnormality.

    Pass: Rated load lifts, holds stationary and lowers under full control through the specified range with no slip, stall, judder, structural distortion or abnormal sound.

    The core capacity demonstration; run before the overload test. Motor rotation and electrical protection tripping are covered under the electrical module (elec).

  • Criticalper your spec

    Witness the overload test at the declared test factor above rated capacity and confirm the equipment sustains and controls the load without failure or permanent set.

    Pass: The declared overload (e.g. static test load per the applicable factor) is sustained for the specified hold time and released with no loss of control, no permanent deformation and no crack or component failure.

    Proves the safety margin above working load. The exact factor and whether static or dynamic comes from the governing code named in the purchase order (item 001).

  • Criticalper your spec

    Witness the load brake hold the rated load stationary at rest and on loss of power without creep or drift.

    Pass: With rated load suspended and drive power removed, the load remains stationary with no measurable descent over the observation period.

    A brake that creeps under load is a dropped-load hazard. This is the load-holding function; general rotating-machinery bearing checks belong to the rotating module (rot).

  • Criticalper your spec

    Witness each hoisting and travel limit switch or travel end stop arrest the corresponding motion at its set position under representative load.

    Pass: Every upper and lower hoist limit and each travel end stop halts motion at its designed position and prevents further travel in that direction.

    Over-hoisting past the top limit or running off the end of travel are classic causes of dropped or derailed loads. Interlock logic and control sequencing are assessed under the controls module (ctrl).

  • Criticalper your spec

    Witness the overload protection device inhibit or arrest lifting when the load exceeds the set threshold, and verify the set point corresponds to the rated capacity.

    Pass: Applying a load above the configured limit causes the overload protector to prevent or stop the lift; the trip point aligns with the rated capacity within the device tolerance.

    Where fitted, the rated-capacity limiter is the in-service defence against overload. Confirm the set point, not merely that a device is present.

  • Majorper your spec

    For conveying equipment, witness the belt or carrying medium track centrally along the full run under representative load without edge contact or drift.

    Pass: The belt or medium runs centred across all rollers and pulleys through a full loaded cycle with no persistent lateral drift, edge fraying or contact with the structure.

    Mistracking causes spillage, edge damage and downtime. Applies only where a conveyor, belt or continuous carrying medium is part of the supply.

  • Critical

    For conveying equipment, witness each emergency pull-cord or lanyard along the run stop the conveyor from any point along its length.

    Pass: Pulling the cord at any tested point stops conveyor motion and latches out, requiring a deliberate reset before restart.

    The pull-cord is the conveyor-specific stop for a person caught at the line. General emergency-stop architecture and reset logic for the wider machine are assessed under the safety-systems module (safe).

Safety

  • Majorper your spec

    Verify anti-collision, buffers, rail end stops, or the guidance and obstacle-detection stop for a self-guided vehicle are fitted and positioned as specified.

    Applies to the mode of the supplied unit — buffers and rail stops on a travelling crane, obstacle-detection stopping on an AGV or stacker. Static presence and position here; the detection stop response is witnessed as a functional test where relevant.

Documentation pack

  • Major

    Verify the signed load-test and overload-test record is compiled, stating the test loads applied, hold times, methods and results.

    This record substantiates the capacity claim for the life of the equipment and any statutory examination that follows. Compilation into the handover pack is confirmed under the documentation module (docs); this item confirms the load-test record itself exists and is complete.

Common failure modes

  • Major

    Confirm the load test was performed on the actual unit being shipped at its final rated configuration, not on a representative or previously tested sample.

    Substituting a type-test certificate or testing a sister unit is a recurring shortcut; the record and any serial numbers on it must match the unit presented for shipment.

  • Major

    Confirm brakes, limits and overload protection are re-checked as still functional after the overload test, not only before it.

    An overload can distort a brake or shift a limit setting; safety devices proven only before the heaviest load may no longer hold at rated load afterwards.

Lifting & transport readiness

Before the test

  • Majorper your spec

    Confirm the lifting/rigging arrangement drawing, rated unit weight and centre-of-gravity data are available before the lift is witnessed.

    The lift cannot be judged safe without the declared weight, sling points and CoG; without these the trial lift is guesswork.

Build & dimensional

  • Criticalper your spec

    Verify the designated lifting points — lugs, eyebolts, trunnions or padeyes — are present, of the type and position shown on the lifting drawing, and free from cracks, deformation, elongation or weld undercut.

    A failed or missing lifting point is a dropped-load hazard; substituted or field-added lugs not on the drawing are a common defect.

  • Majorper your spec

    Verify each lifting point is marked with its rated capacity (WLL/SWL) where the arrangement requires it, and that the marking is legible and consistent with the lifting drawing.

    Unmarked or mismarked capacity leads riggers at site to over- or under-rate a point; the marking must match the design, not the sling.

  • Majorper your spec

    Verify the centre of gravity is marked on the unit where the arrangement calls for it and that its position agrees with the value stated on the lifting/shipping documentation.

    An unmarked or wrongly placed CoG causes the load to tilt or swing on first lift; discrepancy between the mark and the paperwork is the item to catch here.

  • Majorper your spec

    Where the unit is designed for forklift handling, verify fork pockets or forkable base members are present, of the specified width, spacing and internal height, and clear of obstruction.

    Pockets sized for the works' forks but not the site's, or blocked by pipework/cabling routed through the base, prevent handling on arrival.

  • Majorper your spec

    Verify tie-down, lashing or securing points are provided as required for the transit mode, are sound, and are positioned so the unit can be restrained without loading unprotected structure.

    Missing lashing points force the forwarder to lash over pipework, panels or machined faces, causing transit damage.

  • Majorper your spec

    Where shock and tilt indicators are specified, verify the required number and type are fitted at the correct locations, are armed/reset with an unbroken initial state, and their serial numbers are recorded.

    Indicators fitted after damage, left un-armed, or with serials unrecorded are worthless for a transit-damage claim; record the baseline at FAT.

Functional tests

  • Criticalper your spec

    Witness a trial lift of the bare, unpacked unit using the designated points and arrangement, and confirm it lifts level and stable within the design sling angles.

    Pass: Unit rises clear and hangs level within the tolerance/tilt stated on the lifting drawing (or visibly level where no figure is given), with no slippage, distortion of lifting points or fouling of the sling arrangement.

    The trial lift before packing is the only chance to prove the lugs, CoG and sling geometry together; a unit that hangs off-level reveals a wrong CoG or misplaced points.

  • Critical

    During the trial lift, verify the lifting points and their surrounding structure show no visible deflection, cracking, paint flaking at welds or permanent set once the load is taken and released.

    Pass: No cracking, permanent deformation or set is visible at any lifting point or its attachment after the unit is lifted and set back down.

    Paint cracking or fresh weld distortion under load indicates an under-strength attachment; this is a witnessed check, not a certification of the design.

Documentation pack

  • Majorper your spec

    Where NDT of the lifting points is claimed or required, verify the examination records (method, extent, acceptance criteria and result) exist and correspond to the actual points fitted to this unit.

    Review-not-certify: confirm the records are present and match the fitted lugs by serial/mark; general fabrication NDT and weld quality belong to the material & fabrication module. Lug-weld NDT is routinely skipped or copied from another unit.

  • Minor

    Witness and record the trial-lift result — points used, sling arrangement, level/tilt observed and any indicator serials and baseline states — as dated evidence.

    The lift record and indicator baseline are the reference against which arrival condition and any drop/tilt claim are later assessed.

Common failure modes

  • Major

    Verify the lifting arrangement does not require slinging over or bearing on fragile appendages — pipework, junction boxes, gauges, motors, guarding or machined faces — and that any such items are cleared or protected on the rigging plan.

    The most frequent lifting damage is a sling bearing on a projecting fitting because the drawing gave no clear route; confirm the route keeps slings off vulnerable parts.

Safety systems

Before the test

  • Majorper your spec

    Confirm the safety-function test schedule identifies every protective function on the machine (each guard interlock, emergency stop, presence-sensing device, two-hand control and safety-rated mode) and states how each will be exercised.

    Safety devices are frequently tested by sample rather than exhaustively; an incomplete function list lets an unverified interlock or e-stop ship.

Build & dimensional

  • Critical

    Verify each emergency-stop actuator is a mushroom-head, latching, manually-reset red device on a yellow background, and that one is within reach of every operator position and control station.

    Reach and correct actuator type are checkable statically; an operator position with no e-stop within reach is a common layout defect. ISO 13850 covers e-stop principles but only cite it if the buyer specification does.

  • Critical

    Verify each movable guard has an interlock device fitted, positively mounted so it cannot be defeated by hand or with a simple tool, and that guarded openings do not permit reaching the hazard.

    Physical fitment and defeat-resistance are static checks; the stopping function itself is verified below. Fitment of fixed guards over rotating parts belongs to the rotating-machinery module.

  • Criticalper your spec

    Verify light curtains and area scanners are the specified resolution and protected height, mounted at or beyond the calculated minimum safety distance from the hazard, with no gaps allowing undetected access around or behind the field.

    Detection capability and mounting distance are dimensional and set the whole device's effectiveness; a curtain mounted too close leaves no time for the machine to stop. ISO 13855 gives the distance calculation but only cite it if the specification does.

  • Critical

    Verify every hazardous-energy isolation point — electrical, hydraulic, pneumatic and stored gravity or spring — is provided, clearly identified, and can be locked in the isolated position.

    Presence and lockability of each isolation point is verifiable at rest; a source that cannot be locked off cannot be made safe for maintenance.

Functional tests

  • Critical

    Witness that opening each interlocked guard while the machine is running brings the guarded hazardous motion to a stop, and that the machine cannot be restarted with the guard open.

    Pass: Opening any interlocked guard stops the associated hazardous motion, and no start command initiates motion while that guard remains open.

    This is the physical stop-on-open behaviour of each guard; the safety-logic wiring and dual-channel monitoring behind it are verified in the controls module.

  • Critical

    Witness that operating each emergency-stop device stops all hazardous motion, and confirm that resetting the device does not by itself restart the machine — a separate deliberate start action is required.

    Pass: Every e-stop, when operated, halts all hazardous motion; releasing and resetting it does not restart motion without a separate start command.

    Function and reset-does-not-restart behaviour are witnessed here; the control-system response time and stop category at the logic level belong to the controls module.

  • Critical

    Witness that interrupting each light curtain or area scanner field during hazardous motion stops that motion, and that the machine cannot be restarted while the field remains broken.

    Pass: Breaking the protective field stops the hazardous motion; motion does not resume while the field is obstructed, and restart requires a deliberate action.

    The trip-to-stop behaviour is the core protective function of a presence-sensing device and must be witnessed for each field.

  • Criticalper your spec

    Where a presence-sensing device is muted or blanked during part of the cycle, witness that muting activates only during the intended non-hazardous phase, ends when that phase ends, and provides an indication that muting is active.

    Pass: Muting or blanking engages only in the specified cycle phase, reverts to full protection outside it, and a muting indicator is active while muted.

    Muting is the most abused safety feature: muting that stays on, triggers early, or has no indicator leaves the hazard exposed while the machine appears protected.

  • Critical

    Where two-hand controls are fitted, witness that hazardous motion requires both actuators pressed within the permitted concurrency window and continuously held, and that releasing either one stops the motion.

    Pass: Motion starts only with both actuators operated near-simultaneously and held; releasing either actuator, or operating one alone, does not initiate or sustain motion.

    Attempt single-hand and tied-down operation as part of the test; a two-hand control that can be defeated by one hand or a wedge gives no protection. ISO 13851 covers two-hand controls but only cite it if the specification does.

  • Criticalper your spec

    Where the equipment includes a robot or programmable manipulator, witness that reduced-speed or safe-operating modes limit motion as specified and that entry into a defined safeguarded zone stops or slows the robot as intended.

    Pass: Reduced-speed mode holds robot motion within the specified limit, and breaching a safeguarded zone produces the specified protective stop or speed reduction.

    Safety-rated speed limits and zone monitoring are the primary safeguards for collaborative or fenced robot cells and are validated by the buyer's zone and speed specification.

  • Criticalper your spec

    For equipment containing a laser source, witness that opening the enclosure or defeating an access interlock removes laser emission, and confirm the enclosure is intact with no unintended apertures allowing beam escape.

    Pass: Opening any interlocked access point or panel terminates laser emission; the enclosure shows no gaps or apertures permitting beam or reflected-beam escape.

    Applies only to equipment with an enclosed laser source. Enclosure integrity and emission-off-on-open are the containment safeguards for an otherwise inaccessible beam. IEC 60825-1 governs laser safety but only cite it if the specification does.

Safety

  • Criticalper your spec

    Verify that isolating each energy source and following any specified residual-energy discharge step leaves no hazardous stored energy — confirm hydraulic and pneumatic pressure is vented, capacitors are discharged, and gravity or spring loads are supported or blocked.

    Isolation alone does not remove trapped energy; an accumulator, sprung mechanism or suspended axis can release after the supply is locked off if no discharge or restraint step is provided.

Documentation pack

  • Minor

    Collect the safety-function validation records for the witnessed tests, together with any risk assessment, safety-device datasheets and laser-classification declaration provided for the machine.

    These records evidence which protective functions were validated at the works and are needed for on-site commissioning and the machine's safety file.

Common failure modes

  • Critical

    Confirm no protective device has been bypassed, jumpered, taped, or otherwise defeated to ease commissioning — inspect for defeated interlocks, blocked curtains, and disabled e-stop or safety channels.

    Safety functions are routinely defeated during factory build to speed adjustment and are sometimes not restored; a bypass left in place ships an unsafe machine that appears compliant.

  • Majorper your spec

    Confirm safety hazard labels, laser-classification and aperture warnings, and isolation-point identification are present, legible, and in a language agreed with the buyer.

    Missing, illegible or wrong-language safety and laser labelling is a frequent shipment defect and can block acceptance or import; laser labels are required only for laser-containing equipment.

Measurement and instrumentation

Before the test

  • Majorper your spec

    Confirm an instrument list or tag schedule is available that names every fitted instrument by tag, type, range and required accuracy, and reconcile it against the instruments actually installed.

    Without a reconciled tag list, missing or substituted instruments go unnoticed and no item below can be judged complete.

  • Majorper your spec

    Confirm the reference instrument used for spot accuracy checks is itself in-date and of adequate accuracy for the tags being verified, and record its identity.

    A reference no better than, or coarser than, the instrument under check cannot prove the reading; this is the fitted-instrument counterpart to the FAT test-equipment calibration checked under pre-FAT readiness.

Build & dimensional

  • Majorper your spec

    Verify each tagged instrument's identification plate or label matches the tag schedule for tag number, model, range and units, and that the tag is legibly and durably marked on the instrument.

    Untagged or mislabelled instruments cannot be maintained, recalibrated or trusted once the equipment is on site.

  • Majorper your spec

    Verify the indicated engineering units and measurement range of each local gauge, dial and display match the buyer specification.

    Instruments scaled in the wrong units (e.g. bar vs psi, degC vs degF) or with an unsuitable range are a frequent and easily missed non-conformity on export equipment.

  • Majorper your spec

    Verify each sensor and instrument is installed at the location, orientation and process connection shown on the P&ID or general arrangement drawing, including isolation and any manifold or root valve.

    Owns sensor placement only; the wiring back to the control system and the control response to the signal are checked under the electrical and controls modules respectively.

  • Majorper your spec

    Verify the sensor mounting suits the measurement — flow elements have the specified straight-run and correct flow direction, thermowells are inserted to the specified depth, and level and pressure tappings are at the correct elevation.

    Correct hardware installed incorrectly still reads wrong; poor placement is a built-in error that no downstream calibration removes.

Functional tests

  • Majorper your spec

    Perform a spot accuracy check on each critical instrument by comparing its indication against the reference instrument at the process condition available during the FAT, and record both readings.

    Pass: Difference between the instrument indication and the reference reading is within the instrument's stated accuracy or the tolerance in the buyer specification, at each point checked.

    A single-point comparison at ambient or idle condition will not exercise the full span; note which points could be checked and which could not.

  • Majorper your spec

    Where an instrument feeds a local or panel display, verify the value shown on the display agrees with the instrument's own indication and with the reference reading.

    Pass: Displayed value tracks the reference reading within the combined stated accuracy of the loop, with no offset, wrong scaling or unit mismatch between field and display.

    Verifies the reading is carried through to where the operator sees it; the display truth is in scope, but alarm and interlock behaviour driven by the value belongs to the controls module.

  • Majorper your spec

    For any instrument that cannot be exercised at a representative process value during the FAT, witness or review a bench or loop calibration record covering its full span rather than a single point.

    Pass: Documented calibration shows as-found and as-left errors within the instrument's stated accuracy across the specified span, with the calibration current and traceable.

    Full-span coverage catches linearity and span errors that a single ambient spot check cannot; accept documentary evidence only where live checking is impractical.

Documentation pack

  • Major

    Collect a valid, in-date calibration certificate for each fitted instrument that shows the tag number, the as-left result, the accuracy achieved and the calibration and due dates.

    An instrument fitted without a current certificate has no evidence of correctness; a certificate that does not carry the tag number cannot be tied to the instrument on the equipment.

  • Majorper your spec

    Verify each calibration certificate states traceability to a recognised national or international measurement standard through the reference equipment used.

    A certificate with a result but no traceable chain is not defensible; ISO/IEC 17025 accreditation of the calibrating body is often required but only cite it where the buyer specification does.

Common failure modes

  • Minor

    Check for calibration certificates whose due date will lapse before the equipment is expected to be commissioned on site.

    Instruments calibrated long before shipment can arrive out of calibration after transit and storage; flag short-dated certificates so recalibration can be planned before start-up.

  • Major

    Check that a certificate exists and reconciles for the specific serialised instrument fitted, not for a different unit of the same model, and that no tag has been left with a generic or template certificate.

    A common substitution is a certificate for one serial number attached to a different installed instrument; match serial numbers, not just model numbers.

  • Majorper your spec

    For instruments with a configurable range or scaling, confirm the range actually configured in the device matches its nameplate, its certificate and the buyer specification.

    A transmitter can be calibrated correctly yet re-ranged afterwards; a field-configured range that disagrees with the specification produces plausible but wrong readings in service.

Performance and capacity

Before the test

  • Criticalper your spec

    Confirm the rated-duty figures to be demonstrated — throughput or capacity, cycle time, consumption, and output-quality acceptance criteria — are written into the purchase order or datasheet and agreed in the FAT protocol before the run.

    Without agreed numbers and a defined test method the performance run degrades into a vague 'ran at rated load' observation that proves nothing at payment time.

  • Majorper your spec

    Confirm the run will use the specified test material, feedstock, or load and the rated operating conditions (speed, setpoints, product grade), and record any deviation from service conditions agreed for the test.

    A performance figure achieved on an easy substitute material or a light load does not represent rated duty; substitutions must be declared and accepted, not discovered afterwards.

  • Major

    Confirm the instruments used to measure throughput, cycle time, and consumption (flow, power, air, and water meters, timers, counters, weighers) are identified and hold valid calibration for the test.

    The performance result is only as trustworthy as the meters that produced it; sensor accuracy against a reference is verified under the instrumentation module, but calibration validity for this run must be confirmed here.

Functional tests

  • Criticalper your spec

    Witness a sustained run at rated capacity for the agreed test duration and record the achieved throughput over that period.

    Pass: Averaged throughput over the full agreed duration meets or exceeds the rated capacity stated on the datasheet or purchase order, within any agreed tolerance, without slowing to sustain the rate.

    Throughput group. A short burst at rated speed is not proof; the figure must hold across the agreed duration. Peak instantaneous rate is not the same as sustained capacity.

  • Majorper your spec

    Measure the cycle time (or takt time) for representative cycles during the sustained run and record the values.

    Pass: Measured cycle time meets or is below the specified cycle time on the datasheet or purchase order, within any agreed tolerance, and is consistent across the sampled cycles rather than met only occasionally.

    Throughput group. Cycle time and throughput are separate claims: a machine can hit its cycle time on a single cycle yet miss sustained throughput once loading, indexing, and reset are included.

  • Majorper your spec

    Confirm the unit holds rated output stably through the run without unplanned stoppages, throughput decay, or manual intervention to keep it running, and record any stoppage with its cause and duration.

    Pass: Rated output is sustained for the agreed duration with no unplanned stop and no downward drift in rate; any stoppage is logged and, if not within the agreed allowance, the run is repeated.

    Throughput group. Frequent micro-stops, creeping rate loss, or an operator nursing the machine all indicate the rated duty is not genuinely met even when the headline number is briefly reached.

  • Majorper your spec

    Measure electrical power drawn by the unit while running at rated load and compare it against the declared consumption figure.

    Pass: Measured power demand at rated load is at or below the declared/guaranteed consumption figure on the datasheet or purchase order, within any agreed tolerance.

    Consumption group. Consumption is checked at load, not idle; an under-declared draw can overload the site supply or breach an energy guarantee. Measured against the declared figure only — connection-point sizing versus the interface drawing belongs to the utilities module.

  • Majorper your spec

    Where the unit consumes compressed air, measure air consumption at rated load and supply pressure and compare it against the declared figure.

    Pass: Measured air consumption (free air delivery) at the specified working pressure and rated load is at or below the declared figure, within any agreed tolerance.

    Consumption group. Applicable only to air-using equipment. Understated air demand starves other equipment on a shared compressor and is a common source of on-site capacity shortfalls.

  • Majorper your spec

    Where the unit consumes process or cooling water (or other declared utility), measure consumption at rated load and compare it against the declared figure.

    Pass: Measured water/utility consumption at rated load and the specified supply conditions is at or below the declared figure, within any agreed tolerance.

    Consumption group. Applicable only where a water or fluid utility is declared. Excess draw can exceed the site's supply or effluent capacity and inflate running cost against the quoted figure.

  • Majorper your specISO 2859-1

    Confirm a sampling plan for output quality — sample size, sampling frequency, acceptance and rejection numbers — is agreed and recorded before the run begins.

    Pass: A written sampling plan with defined sample size, frequency, and accept/reject criteria is fixed and signed off before output is sampled, not adjusted after results are seen.

    Output-quality group. Agreeing the plan afterwards lets a marginal run be passed by relaxing the criteria. ISO 2859-1 governs attribute sampling by acceptance level and is cited only where the buyer's plan is built on it; otherwise use the agreed plan and set standardRef to null.

  • Criticalper your spec

    During the sustained run, sample the output to the agreed plan and check each sample against the buyer's output acceptance criteria, recording the result of each sample.

    Pass: Sampled output meets the buyer's specified acceptance criteria and the run stays within the acceptance number of the agreed sampling plan; the lot is not accepted if the rejection number is reached.

    Output-quality group. Throughput at rated speed is worthless if the product coming off is out of tolerance; output must be judged during the capacity run, not on a separate hand-picked sample.

  • Majorper your spec

    Record the reject, scrap, or rework rate observed over the sustained run and compare it against the agreed maximum.

    Pass: Reject/scrap rate over the run is at or below the maximum stated in the purchase order or agreed in the FAT protocol; if no figure is specified, the rate is recorded for acceptance by agreement.

    Output-quality group. A machine that meets throughput only by producing a high scrap fraction has not met effective capacity; the good-output rate is the figure that matters on site.

Documentation pack

  • Major

    Collect the signed performance test record — achieved throughput and cycle time, measured consumption figures, and the completed output-sampling results with reject rate — noting test material, operating conditions, and instruments used.

    This signed record is the shipment-payment evidence that rated duty was actually demonstrated; without the test conditions and instruments noted, the figures cannot be defended or reproduced on site.

Common failure modes

  • Majorper your spec

    Confirm the demonstrated rate was not achieved by running above the specified operating parameters (over-speed, over-temperature, over-pressure, or a setpoint outside the datasheet) purely to pass the test.

    Rated output is only valid at rated conditions; pushing the machine past its specified settings to reach the number hides a real capacity shortfall and shortens equipment life in service.

Utilities and site interfaces

Before the test

  • Criticalper your spec

    Verify the current approved interface drawings — connection-point schedule, utility list, general-arrangement and foundation/anchor-bolt drawing — are present at the FAT at the revision the buyer's site works are being built to.

    Every interface check below is only as good as the drawing revision witnessed against; site foundations and service runs are committed against these drawings, and a superseded revision invalidates the comparison.

Build & dimensional

  • Criticalper your spec

    Verify each utility connection point provided on the unit — electrical entry, compressed air, water supply and return, steam, drain and any other declared service — is present and matches the connection-point schedule for service type.

    A missing or mis-typed connection point (for example a service the buyer's contractor has not run, or the wrong medium at a port) leaves the unit uninstallable until site works are altered.

  • Majorper your spec

    Measure the size and confirm the termination type of each connection point (bore/DN, thread form or flange rating and standard, cable-entry size, hose fitting) against the interface schedule.

    A port at the wrong size, thread standard or flange rating forces on-site adaptors or rework; thread/flange standards (for example metric versus imperial, or differing flange tables) are order-dependent and must match what the site pipework is built to.

  • Majorper your spec

    Measure the location of each connection point (side, height and offset from a stated datum) against the interface drawing.

    Connection points that are the right type and size but in the wrong position still clash with pre-installed service runs; the buyer's contractor lays pipework and cable trays to these coordinates ahead of delivery.

  • Majorper your spec

    Measure the overall installed footprint — length, width, height and any transit-swing or door-opening envelope — against the general-arrangement drawing.

    An oversized footprint or an unstated opening/service envelope will not fit the prepared bay; dimensions are checked here against the GA, whereas structural dimensional conformity of the fabrication is covered by the structural module.

  • Criticalper your spec

    Verify the anchor-bolt pattern — hole positions, hole diameters, bolt-hole spacing and edge distances at the base — against the foundation/anchor-bolt drawing the buyer's foundation is cast to.

    Cast-in anchor bolts or drilled fixings are set before the unit arrives; a base hole pattern that does not match the foundation template cannot be corrected on site without breaking out concrete. This checks the interface pattern against the drawing, not the adequacy of the anchoring design.

  • Majorper your spec

    Verify maintenance-access and operating clearances shown on the layout — panel swing, door and cover opening arc, withdrawal space for removable assemblies, and personnel access routes — are physically achievable on the built unit.

    Clearances reserved on the site layout are useless if the built unit needs more room to open a door or withdraw a component; this surfaces only when the arcs and pull-out spaces are checked on the actual hardware.

  • Majorper your spec

    Verify the declared connected/installed load for each utility — electrical demand, compressed-air flow, water flow, steam demand and drain discharge — is stated on the interface documentation in the units the site design uses.

    The buyer sizes incoming supplies, drains and services from these declared figures; a load left unstated or given in ambiguous units means the site service cannot be sized with confidence.

Functional tests

  • Majorper your spec

    During the at-load performance run, measure the actual consumption of each utility (electrical demand, air and water flow, steam demand, drain discharge as applicable) at the connection points and compare it against the declared figure on the interface documentation.

    Pass: Measured consumption of each utility at duty is at or within the tolerance of the declared value on the interface documentation; no utility materially exceeds its declared demand.

    A unit that draws more than declared can overload a supply or drain sized to the datasheet. This owns the declared-versus-measured interface conformity; the at-load performance run itself and its throughput/output acceptance are covered by the performance module — witness this measurement during that run rather than staging a separate one.

Documentation pack

  • Major

    Collect the final connection-point and utility schedule marked as-built, recording any connection type, size, position or declared-load values that differ from the issued interface drawings.

    The as-built interface record is what the site installation and services contractors work to; undocumented deviations from the issued drawings are discovered at connection, after supplies and pipework are committed.

  • Minor

    Collect the measured-consumption record from the at-load run for each utility, noting the measurement point, instrument used and the value against the declared figure.

    This record is the buyer's evidence for final sizing and commissioning of the incoming supplies and drains, and the baseline for later service metering.

Common failure modes

  • Major

    Sample-check that connection points are not obstructed by adjacent structure, framework or other services on the built unit, so each remains accessible for the site connection shown on the interface drawing.

    A port that is correct in type, size and nominal position but boxed in by nearby brackets, guarding or another pipe cannot be reached with a spanner or coupling at site; this passes a drawing check yet fails at installation.

  • Major

    Verify that connection points shared or ganged on the drawing (for example a common return header, a single air inlet feeding multiple circuits, or a combined drain) are physically arranged on the unit as the interface drawing shows, not split or relocated during build.

    Build-stage relocation of a shared connection — splitting one declared inlet into two, or moving a common drain — quietly changes the number and position of site tie-ins the contractor has prepared for.

This is a starting point for a factory acceptance test, not engineering advice. Adapt it to your specification and contract, and have a qualified engineer confirm anything safety-critical.

Different equipment? Build a checklist for any equipment

How this checklist is built

Every factory acceptance test decomposes into a bounded set of attribute checks — rotating parts, electrical power, pressure systems, controls, safety, and so on — plus a few universal checks that apply to any equipment. Selecting an attribute adds its checks; the result is deterministic, so the same selections always produce the same checklist.

Frequently asked questions

What is a factory acceptance test?

A factory acceptance test (FAT) is a structured inspection carried out at the supplier's works, before shipment and before the balance payment is released, to verify the equipment is built and performs as specified. It is the last point in the order where a fault is corrected by the people who built the machine, on their own premises, at their own cost.

How is the checklist assembled?

You tick the attributes your equipment has — a powered drive, a hydraulic circuit, a controls package, product-contact surfaces, and so on. Each attribute adds a set of acceptance checks, and three universal check sets (readiness, documentation, packing) are always included. The composition is deterministic.

Does this replace an independent inspection?

No. It is a starting point for scoping a factory acceptance test, not engineering advice or a substitute for a witnessed inspection. Sinospect can attend the FAT at the Chinese factory on your behalf, witness the tests, and issue a report — the checklist is where that scope begins.

Want this witnessed at the factory?

Sinospect attends factory acceptance tests at Chinese manufacturers on behalf of foreign buyers — witnessing the tests, checking the build against your specification, and issuing a report with photographs before the balance is released.

Talk to us about a FAT